Line 1: | Line 1: |
== Check list for ITMX vacuum in August, 2018 == | == Check list for ITMX vacuum in Summer of 2018 == |
Line 8: | Line 8: |
* 2018/8/27 : Closing EXC * 2018/8/??- : pump down * 2018/8/??: leak check |
* 2018/8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。 * 2018/8/21: IPリリース、調整 * 2018/8/27(Mon) : Closing IXC、同日cryostatの掃除をする。 * 2018/8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き * 2018/9/3-5: leak check * 2018/9/5-7: φ800のフランジ開け * 9/10: 停電対策で真空関係の対応 |
Line 23: | Line 27: |
* Tcam for ITMX (2018/8/?? Inoue) -> (2018/8/XX planed) * Vacuum gage for IXA (2018/4/XX Inoue) -> (2018/8/XX planed) |
* Tcam for ITMX (2018/8/?? Yokozawa) -> (2018/8/22 planed) * Vacuum gage for KAGRA (2018/8/XX Tomaru) -> (2018/8/XX planed) |
Line 26: | Line 30: |
* 真空槽の傾きをdial gaugeで測る。 (2018/8/XX Tomaru, Suzuki, Kimura) -> (2018/8/XX planed) * ITMX 機器制御 for status monitors (2018/8/XX Tomaru, Suzuki, Kimura) -> (2018/8/XX planed) * Vacuum gauge monitor at the control room (2018/8/XX Uchiyama, Kimura, Inoue, Miyoki) -> (2018/8/XX planed) |
* 真空槽の傾きをdial gaugeで測る。 (2018/8/XX Kimura) -> (2018/8/27~ planed, measured from 8/30~) * ITMX 機器制御 for status monitors (2018/8/XX Tomaru) -> (2018/8/XX planed) * Vacuum gauge monitor at the control room (2018/8/XX Tomaru) -> (2018/8/XX planed) |
Line 31: | Line 35: |
=== その他追加項目 === | === 真空引き後、追加項目 === |
Line 33: | Line 37: |
* Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Tomaru) * 真空引き後、防振系の動作チェック (2018/X/XX, Enomoto) -> (2018/8/XX planed) * IXA ゲードバルブの動作チェック (2018/X/XX, Uchiyama) -> (2018/8/XX planed) |
* 真空引き後、防振系の動作チェック (2018/X/XX, Fujii) -> (2018/8/XX planed) * Xarmコミッショニング時、IXA ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed) * Xarmコミッショニング時、BS ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed) |
Line 38: | Line 43: |
* --(Fishing rodの動作チェック)-- (2018/4/6, Takahashi) * --(Tuning of BF)-- (2018/3/26, Takahashi) * --(Tuning of F3)-- (2018/3/27, Takahashi) * --(Tuning of TF)-- (2018/3/27, Takahashi) * --(Tuning of position of BF damper)-- (2018/3/28, Takahashi) * --(Centering IP)-- (2018/3/27, Takahashi) * --(BF yaw picomotorの動作確認)-- (2018/4/11, Takahashi) * --(トップ真空槽蓋閉め)-- (2018/3/28, Takahashi) * --(トップ真空槽ボルト閉め)-- (2018/4/11, Kimura) * --(クロス菅ボルト閉め)-- (2018/4/11, Kimura) * --(IPの制御)-- (2018/4/13, Takahashi) * --(BFのdamping制御)-- (2018/4/2, Okutomi) -> (2018/X/XX planed) * --(BF FRによるmirrorの高さ調整)-- (2018/4/5, Takahashi) * --(BF yaw picomotorによるmirrorのyaw調整)-- (2018/4/5, Ushiba) * --(事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。)-- (2018/4/5, Ushiba) * --(BF温度計つなぎこみ)-- (2018/4/6, Takahashi, Ushiba) |
* IPリリース、調整 (2018/X/XX, Okutomi) -> (2018/8/21 planed) * Fishing rodの動作チェック (2018/X/XX, Takahashi) * Tuning of BF (2018/X/XX, Takahashi) * Tuning of F3 (2018/X/XX, Takahashi) * Tuning of TF (2018/X/XX, Takahashi) * Tuning of position of BF damper (2018/X/XX, Takahashi) * Centering IP (2018/X/XX, Takahashi) * BF yaw picomotorの動作確認 (2018/X/XX, Takahashi) * トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro) * トップ真空槽ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro) * クロス菅ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro) * IPの制御 (2018/X/XX, Takahashi) * BFのdamping制御 (2018/X/XX, Okutomi) -> (2018/X/XX planed) * BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/8/?? planed) * BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Ushiba) -> (2018/8/?? planed) * 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, Ushiba) * BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/8/?? planed) |
Line 57: | Line 64: |
* --(8K および 80Kシールドにつける窓類の取り付け)-- (2018/4/11 Tomaru) * --(輻射シールドのシャッター開確認)-- (2018/4/5, Ushiba) * --(当該部のSuper Insulation(SI)取り外し確認)-- (2018/4/12, Kimura) * --(鏡板取付前の変換フランジ取付)-- (2018/4/11 Kimura) * --(鏡板取付後のビューポート取付)-- (2018/4/12, Akutsu) * Oplev用の島取付 (2018/X/XX, Akutsu) -> (2018/4/12 planed) |
* 8K および 80Kシールドにつける窓類の取り付け (2018/X/XX Kimura) -> (2018/8/27,28 planed) * 輻射シールドのシャッター開確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed) * 当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed) * --(鏡板取付前の変換フランジ取付)-- (2018/8/10 Kimura) * 鏡板取付後のビューポート取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed) * Oplev用の島取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed) * Q massの取り付け (2018/X/XX Kimura) -> (2018/8/27-31 planed) |
Line 64: | Line 72: |
=== EXAチェンバー周り (Inoue) === * --(フォトディテクターの取り外し)-- (2018/3/26, Yokozawa) * --(GigEカメラの前の真空窓取り外しと取り付け)-- (2018/4/9, Inoue) |
=== IXV支持構造体のセット確認 === 1. コーンベローズ脚ロックナットの固定確認 3箇所 (但し、手締め)(2018/X/XX, Kimura) -> (2018/8/30 planed) * チェンバー本体用 3箇所 <- 今回は固定のまま (2018/X/XX, Kimura) -> (2018/8/30 planed) |
Line 68: | Line 76: |
=== EXV支持構造体のセット確認 === 1. --(コーンベローズ脚ロックナットの固定確認 3箇所)-- (但し、手締め)(2018/4/12, 木村) * --(チェンバー本体用 3箇所 <- 真空引き前にフリーにする)-- 今回はやらない |
=== WAB (阿久津)at IXC === * Type-A+cryopayloadがbalance地点に調整されしだい、finalize(2018/X/XX, Akutsu)-> (2018/8/22以降) * finalize前に、 * Type-A+cryopayloadがbalance地点に調整されているか * Assembly frameが動く状態になっているか * やる作業としては * WABを定位置に固定、ヒートリンクなどを取り付ける === NAB(阿久津)at IXA === * --(NABがリリースされているか?(2018/08/09, Akutsu))-- * NAB/Tcam frameについている白テープを全て剥がしたか? (Uchiyama??) * NABのQ-factor測定の状況は確認したか (2018/08/23, Akutsu) |
Line 77: | Line 94: |
* --(EXA 鏡板閉止)-- (2018/4/12, Kimura) * --(EXV top flange: VIS group)-- (2018/4/11, Kimura) * --(EXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/3/28, Takahashi) * --(クロス菅鏡板2箇所: CRY group, VIS group)-- (2018/4/11 Kimura) * --(ICF253送風機接続ポート: CRY group)-- (2018/4/11 Kimura) * --(EXC鏡板箇所: CRY group)-- (2018/4/11 Kimura) * --(EXC鏡板残り1箇所: CRY group)-- (2018/4/12, Kimura) <- 鏡板閉止完了 * --(EXC 鏡板View''''''Port 用変換フランジ1箇所:CRY group)-- (2018/4/11, Kimura) * --(EXC View''''''Port 3箇所(鏡板1箇所、容器2箇所): AOS)-- (2018/4/12, Akutsu) * --(冷凍機NW-50フランジ交換 3箇所: CRY group)-- (2018/4/10, Kimura) * --(ICF152送風機接続ポート 2箇所: CRY group)-- (2018/4/10 Kimura) * --(EXA ICF152 2箇所: cal group)-- (2018/4/5-6, Inoue) * --(ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group)-- (2018/4/11 Kimura) * --(EYC~クロス管挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura) * --(EYA~EYC間レーザーハザード用挿しフランジ取り外しとフランジ再締結)-- (2018/3/12, Kimura) * --(EYAのEYC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用))-- (2018/3/12, Kimura) |
* IXA 鏡板閉止 (2018/X/XX, Kimura) * IXV top flange: VIS group (2018/X/XX, Kimura) * IXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/X/XX, Takahashi) * クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX Kimura) * ICF253送風機接続ポート: CRY group (2018/X/XX Kimura) * IXC鏡板箇所: CRY group (2018/X/XX Kimura) * IXC鏡板残り1箇所: CRY group (2018/X/XX, Kimura) <- 鏡板閉止完了 * IXC 鏡板View''''''Port 用変換フランジ1箇所:CRY group (2018/X/XX, Kimura) * IXC View''''''Port 3箇所(鏡板1箇所、容器2箇所): AOS (2018/X/XX, Akutsu --> Ushiba??) * 冷凍機NW-50フランジ交換 3箇所: CRY group (2018/X/XX, Kimura) * ICF152送風機接続ポート 2箇所: CRY group (2018/X/XX, Kimura) * IXA ICF152 2箇所: cal group (2018/X/XX, Inoue) * ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group (2018/X/XX, Kimura) * IYC~クロス管挿しフランジ取り外しとフランジ再締結 (2018/X/XX, Kimura) * IXA~IXC間レーザーハザード用挿しフランジ取り外しとフランジ再締結 (2018/3/12, Kimura) * IXAのIXC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用) (2018/3/12, Kimura) * IXAの上ぶた (NAB/TCam/BafflePDs) * IXAの両サイドフランジ (NAB/TCam/BafflePDs) * IXAのICF70 viewport。3km腕側で、-Y側。 (NAB) * IXAの上側のICF203部分。コネクタつきのフランジに交換した (BafflePD) |
Line 96: | Line 117: |
i. --(真空計2台 ON)-- (2018/4/13, Kimura) * --(粗挽きポンプスタート)-- (2018/4/13, Kimura) * 大まかなリークチェック (2018/X/XX, Kimura) -> (2018/4/13 planed) * --(ターボポンプ冷却水循環装置スタート)-- (2018/4/13, Kimura) * ターボポンプスタート (2018/X/XX, Kimura) -> (2018/4/16 planed) |
i. 真空計2台 ON (2018/X/XX, Kimura) * 粗挽きポンプスタート (2018/X/XX, Kimura) * 大まかなリークチェック (2018/X/XX, Kimura) * ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura) * ターボポンプスタート (2018/X/XX, Kimura) |
Line 102: | Line 123: |
* リーク試験 (2018/4/XX, Kimura) -> (2018/4/18-20 planed) | * リーク試験 (2018/4/XX, Kimura) |
Line 105: | Line 126: |
* ゲートバルブ動作試験 (2018/4/XX, Kimura) -> (2018/4/20 planed) | * ゲートバルブ動作試験 (2018/4/XX, Kimura) |
Line 115: | Line 136: |
* リリース関係 * --(PFのリリース(16箇所))-- (2018/4/12, Tomaru) * --(MNのリリース(16箇所))-- (2018/4/12, Tomaru) * --(MNRのリリース(16箇所))-- (2018/4/12, Tomaru) * --(IMのリリース(6箇所))-- (2018/4/12, Tomaru) * --(IMRのリリース(16箇所))-- (2018/4/12, Tomaru) * --(TMのリリース(16箇所))-- (2018/4/12, Tomaru) * --(TMRのリリース(15箇所))-- (2018/4/12, Tomaru) |
* Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba) |
Line 125: | Line 138: |
* --(TM Op''''''Lev Pitch)-- (2018/3/30, Ushiba, Tomaru) * --(TM Op''''''Lev Yaw)-- (2018/3/30, Ushiba, Tomaru) * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) -> (2018/4/16 planed) |
* TM Op''''''Lev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * TM Op''''''Lev Yaw (2018/X/XX, Ushiba, Tomaru) * TM Op''''''Lev Length (2018/X/XX, Ushiba, Tomaru) |
Line 130: | Line 143: |
* --(IM PS H1)-- (2018/4/5, Ushiba) * --(IM PS H2)-- (2018/4/5, Ushiba) * --(IM PS H3)-- (2018/4/5, Ushiba) * --(IM PS V1)-- (2018/4/5, Ushiba) * --(IM PS V2)-- (2018/4/5, Ushiba) * --(IM PS V3)-- (2018/4/5, Ushiba) |
* IM PS H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed) * IM PS H2 (2018/X/XX, Ushiba) * IM PS H3 (2018/X/XX, Ushiba) * IM PS V1 (2018/X/XX, Ushiba) * IM PS V2 (2018/X/XX, Ushiba) * IM PS V3 (2018/X/XX, Ushiba) |
Line 137: | Line 150: |
* --(MN PS H1)-- (2018/4/5, Ushiba) * --(MN PS H2)-- (2018/4/6, Ushiba) * --(MN PS H3)-- (2018/4/5, Ushiba) * --(MN PS V1)-- (2018/4/5, Ushiba) * --(MN PS V2)-- (2018/4/5, Ushiba) * --(MN PS V3)-- (2018/4/5, Ushiba) |
* MN PS H1 (2018/X/XX, Ushiba) * MN PS H2 (2018/X/XX, Ushiba) * MN PS H3 (2018/X/XX, Ushiba) * MN PS V1 (2018/X/XX, Ushiba) * MN PS V2 (2018/X/XX, Ushiba) * MN PS V3 (2018/X/XX, Ushiba) |
Line 144: | Line 157: |
* MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/4/12 planed) * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto) -> (2018/4/12 planed) |
* MN Op''''''Lev Pitch (2018/X/XX, Miyamoto) -> (2018/X/XX planed) * MN Op''''''Lev Yaw (2018/X/XX, Miyamoto) |
Line 148: | Line 161: |
* 温度計B (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計C (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計D (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計E (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計F (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計G (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) * 温度計H (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
* 温度計B (2018/X/XX, Ushiba, Tomaru) * 温度計C (2018/X/XX, Ushiba, Tomaru) * 温度計D (2018/X/XX, Ushiba, Tomaru) * 温度計E (2018/X/XX, Ushiba, Tomaru) * 温度計F (2018/X/XX, Ushiba, Tomaru) * 温度計G (2018/X/XX, Ushiba, Tomaru) * 温度計H (2018/X/XX, Ushiba, Tomaru) |
Line 158: | Line 171: |
* --(TM アクチュエータ H1)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H2)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H3)-- (2018/4/5, Ushiba) * --(TM アクチュエータ H4)-- (2018/4/5, Ushiba) |
* TM アクチュエータ H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed) * TM アクチュエータ H2 (2018/X/XX, Ushiba) * TM アクチュエータ H3 (2018/X/XX, Ushiba) * TM アクチュエータ H4 (2018/X/XX, Ushiba) |
Line 163: | Line 176: |
* --(IM アクチュエータ H1)-- (2018/4/5, Ushiba) * --(IM アクチュエータ H2)-- (2018/4/5, Ushiba) * --(IM アクチュエータ H3)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V1)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V2)-- (2018/4/5, Ushiba) * --(IM アクチュエータ V3)-- (2018/4/5, Ushiba) |
* IM アクチュエータ H1 (2018/X/XX, Ushiba) * IM アクチュエータ H2 (2018/X/XX, Ushiba) * IM アクチュエータ H3 (2018/X/XX, Ushiba) * IM アクチュエータ V1 (2018/X/XX, Ushiba) * IM アクチュエータ V2 (2018/X/XX, Ushiba) * IM アクチュエータ V3 (2018/X/XX, Ushiba) |
Line 170: | Line 183: |
* --(MN アクチュエータ H1)-- (2018/4/5, Ushiba) * --(MN アクチュエータ H2)-- (2018/4/5, Ushiba) * --(MN アクチュエータ H3)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V1)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V2)-- (2018/4/5, Ushiba) * --(MN アクチュエータ V3)-- (2018/4/5, Ushiba) |
* MN アクチュエータ H1 (2018/X/XX, Ushiba) * MN アクチュエータ H2 (2018/X/XX, Ushiba) * MN アクチュエータ H3 (2018/X/XX, Ushiba) * MN アクチュエータ V1 (2018/X/XX, Ushiba) * MN アクチュエータ V2 (2018/X/XX, Ushiba) * MN アクチュエータ V3 (2018/X/XX, Ushiba) |
Line 177: | Line 190: |
* SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) 今回は無し | * SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru) |
Line 179: | Line 192: |
* --(MN moving mass1)-- (2018/4/5, Ushiba) * --(MN moving mass2)-- (2018/4/5, Ushiba) * --(PF moving mass1)-- (2018/4/5, Ushiba) * --(PF moving mass2)-- (2018/4/5, Ushiba) * ダンピング制御 * MN, BFを用いたヒエラリカル制御 (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed) |
* MN moving mass1 (2018/8/XX, Ushiba) * MN moving mass2 (2018/8/XX, Ushiba) * PF moving mass1 (2018/8/XX, Ushiba) * PF moving mass2 (2018/8/XX, Ushiba) |
Check list for ITMX vacuum in Summer of 2018
- Term: ~2018/8/27
Schedule
- 2018/8/16(Thur) 12:30 meeting at fan hut.
- 2018/8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
- 2018/8/21: IPリリース、調整
- 2018/8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
- 2018/8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
- 2018/9/3-5: leak check
- 2018/9/5-7: φ800のフランジ開け
- 9/10: 停電対策で真空関係の対応
Each item should have following format;
- item (checked date, checked person)
Once the item has been checked, it will be like:
item (2018/8/20, Somebody)
Preparation of monitors during pump down
Tcam for ITMX (2018/8/?? Yokozawa) -> (2018/8/22 planed)
Vacuum gage for KAGRA (2018/8/XX Tomaru) -> (2018/8/XX planed)
真空槽の傾きをdial gaugeで測る。 (2018/8/XX Kimura) -> (2018/8/27~ planed, measured from 8/30~)
ITMX 機器制御 for status monitors (2018/8/XX Tomaru) -> (2018/8/XX planed)
Vacuum gauge monitor at the control room (2018/8/XX Tomaru) -> (2018/8/XX planed)
真空引き後、追加項目
真空引き後、防振系の動作チェック (2018/X/XX, Fujii) -> (2018/8/XX planed)
Xarmコミッショニング時、IXA ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)
Xarmコミッショニング時、BS ゲードバルブの動作チェック (2018/X/XX, Kimura) -> (2018/9/XX planed)
Type-A tower (高橋)
IPリリース、調整 (2018/X/XX, Okutomi) -> (2018/8/21 planed)
- Fishing rodの動作チェック (2018/X/XX, Takahashi)
- Tuning of BF (2018/X/XX, Takahashi)
- Tuning of F3 (2018/X/XX, Takahashi)
- Tuning of TF (2018/X/XX, Takahashi)
- Tuning of position of BF damper (2018/X/XX, Takahashi)
- Centering IP (2018/X/XX, Takahashi)
- BF yaw picomotorの動作確認 (2018/X/XX, Takahashi)
トップ真空槽蓋閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
トップ真空槽ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
クロス菅ボルト閉め (2018/X/XX, Takahashi) -> (2018/8/30 planed by Mira-pro)
- IPの制御 (2018/X/XX, Takahashi)
BFのdamping制御 (2018/X/XX, Okutomi) -> (2018/X/XX planed)
BF FRによるmirrorの高さ調整 (2018/X/XX, Takahashi) -> (2018/8/?? planed)
BF yaw picomotorによるmirrorのyaw調整 (2018/X/XX, Ushiba) -> (2018/8/?? planed)
- 事前にTypeA、Cryopayloadのアラインメント機構が動くかどうか確認する。 (2018/X/XX, Ushiba)
BF温度計つなぎこみ (2018/X/XX, Takahashi, Ushiba) -> (2018/8/?? planed)
鏡板閉止 (Kimura)
8K および 80Kシールドにつける窓類の取り付け (2018/X/XX Kimura) -> (2018/8/27,28 planed)
輻射シールドのシャッター開確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)
当該部のSuper Insulation(SI)取り外し確認 (2018/X/XX Kimura) -> (2018/8/27,28 planed)
鏡板取付前の変換フランジ取付 (2018/8/10 Kimura)
鏡板取付後のビューポート取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)
Oplev用の島取付 (2018/X/XX, Ushiba) -> (2018/8/27,28 planed)
Q massの取り付け (2018/X/XX Kimura) -> (2018/8/27-31 planed)
IXV支持構造体のセット確認
コーンベローズ脚ロックナットの固定確認 3箇所 (但し、手締め)(2018/X/XX, Kimura) -> (2018/8/30 planed)
チェンバー本体用 3箇所 <- 今回は固定のまま (2018/X/XX, Kimura) -> (2018/8/30 planed)
WAB (阿久津)at IXC
Type-A+cryopayloadがbalance地点に調整されしだい、finalize(2018/X/XX, Akutsu)-> (2018/8/22以降)
- finalize前に、
- Type-A+cryopayloadがbalance地点に調整されているか
- Assembly frameが動く状態になっているか
- やる作業としては
- WABを定位置に固定、ヒートリンクなどを取り付ける
- finalize前に、
NAB(阿久津)at IXA
NABがリリースされているか?(2018/08/09, Akutsu)
- NAB/Tcam frameについている白テープを全て剥がしたか? (Uchiyama??)
- NABのQ-factor測定の状況は確認したか (2018/08/23, Akutsu)
真空引き開始前後 (木村)
- 真空フランジを開放し、再度閉止した箇所の確認(リーク試験箇所の確定に必要な情報です。)
- グループ毎の申告による
- IXA 鏡板閉止 (2018/X/XX, Kimura)
- IXV top flange: VIS group (2018/X/XX, Kimura)
IXV ICF flange交換 ICF203/NW50 変換フランジ -> ICF203ブランクフランジ)-- : VIS group (2018/X/XX, Takahashi)
- クロス菅鏡板2箇所: CRY group, VIS group (2018/X/XX Kimura)
- ICF253送風機接続ポート: CRY group (2018/X/XX Kimura)
- IXC鏡板箇所: CRY group (2018/X/XX Kimura)
IXC鏡板残り1箇所: CRY group (2018/X/XX, Kimura) <- 鏡板閉止完了
IXC 鏡板ViewPort 用変換フランジ1箇所:CRY group (2018/X/XX, Kimura)
IXC ViewPort 3箇所(鏡板1箇所、容器2箇所): AOS (2018/X/XX, Akutsu --> Ushiba??)
- 冷凍機NW-50フランジ交換 3箇所: CRY group (2018/X/XX, Kimura)
- ICF152送風機接続ポート 2箇所: CRY group (2018/X/XX, Kimura)
- IXA ICF152 2箇所: cal group (2018/X/XX, Inoue)
- ICF253ガスケット交換(リークの疑い有り)1箇所: CRY group (2018/X/XX, Kimura)
- IYC~クロス管挿しフランジ取り外しとフランジ再締結 (2018/X/XX, Kimura)
- IXA~IXC間レーザーハザード用挿しフランジ取り外しとフランジ再締結 (2018/3/12, Kimura)
- IXAのIXC側ベローズ締結部(寺田さん、内山さんによるビーム位置測定で使用) (2018/3/12, Kimura)
- IXAの上ぶた (NAB/TCam/BafflePDs)
- IXAの両サイドフランジ (NAB/TCam/BafflePDs)
- IXAのICF70 viewport。3km腕側で、-Y側。 (NAB)
- IXAの上側のICF203部分。コネクタつきのフランジに交換した (BafflePD)
- グループ毎の申告による
- 真空引き
- 真空計2台 ON (2018/X/XX, Kimura)
- 粗挽きポンプスタート (2018/X/XX, Kimura)
- 大まかなリークチェック (2018/X/XX, Kimura)
- ターボポンプ冷却水循環装置スタート (2018/X/XX, Kimura)
- ターボポンプスタート (2018/X/XX, Kimura)
- リーク試験 (2018/4/XX, Kimura)
(リーク判定 < 1x10-10 Pa・m3/s)
- ゲートバルブ動作試験 (2018/4/XX, Kimura)
- (温度・圧縮機のモニター)
スタートさせる (2018/XX/XX, 都丸、麻生) -> (2018/X/XX planed)
温度・圧縮機のループテスト (2018/XX/XX, 都丸、麻生、木村) -> 冷却開始前までに予定
Cryo payload (都丸、牛場)
- Cryo payload EQ stopの隙間のチェック5mm程度 (2018/X/XX, Ushiba)
- センサーチェック
TM OpLev Pitch (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
TM OpLev Yaw (2018/X/XX, Ushiba, Tomaru)
TM OpLev Length (2018/X/XX, Ushiba, Tomaru)
IM PS H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)
- IM PS H2 (2018/X/XX, Ushiba)
- IM PS H3 (2018/X/XX, Ushiba)
- IM PS V1 (2018/X/XX, Ushiba)
- IM PS V2 (2018/X/XX, Ushiba)
- IM PS V3 (2018/X/XX, Ushiba)
- MN PS H1 (2018/X/XX, Ushiba)
- MN PS H2 (2018/X/XX, Ushiba)
- MN PS H3 (2018/X/XX, Ushiba)
- MN PS V1 (2018/X/XX, Ushiba)
- MN PS V2 (2018/X/XX, Ushiba)
- MN PS V3 (2018/X/XX, Ushiba)
MN OpLev Pitch (2018/X/XX, Miyamoto) -> (2018/X/XX planed)
MN OpLev Yaw (2018/X/XX, Miyamoto)
温度計A (2018/X/XX, Ushiba, Tomaru) -> (2018/X/XX planed)
- 温度計B (2018/X/XX, Ushiba, Tomaru)
- 温度計C (2018/X/XX, Ushiba, Tomaru)
- 温度計D (2018/X/XX, Ushiba, Tomaru)
- 温度計E (2018/X/XX, Ushiba, Tomaru)
- 温度計F (2018/X/XX, Ushiba, Tomaru)
- 温度計G (2018/X/XX, Ushiba, Tomaru)
- 温度計H (2018/X/XX, Ushiba, Tomaru)
- アクチュエータチェック
TM アクチュエータ H1 (2018/X/XX, Ushiba) -> (2018/X/XX planed)
- TM アクチュエータ H2 (2018/X/XX, Ushiba)
- TM アクチュエータ H3 (2018/X/XX, Ushiba)
- TM アクチュエータ H4 (2018/X/XX, Ushiba)
- IM アクチュエータ H1 (2018/X/XX, Ushiba)
- IM アクチュエータ H2 (2018/X/XX, Ushiba)
- IM アクチュエータ H3 (2018/X/XX, Ushiba)
- IM アクチュエータ V1 (2018/X/XX, Ushiba)
- IM アクチュエータ V2 (2018/X/XX, Ushiba)
- IM アクチュエータ V3 (2018/X/XX, Ushiba)
- MN アクチュエータ H1 (2018/X/XX, Ushiba)
- MN アクチュエータ H2 (2018/X/XX, Ushiba)
- MN アクチュエータ H3 (2018/X/XX, Ushiba)
- MN アクチュエータ V1 (2018/X/XX, Ushiba)
- MN アクチュエータ V2 (2018/X/XX, Ushiba)
- MN アクチュエータ V3 (2018/X/XX, Ushiba)
- SBS ダンピングコイル(V1-V4) (2018/X/XX, Ushiba, Tomaru)
- MN moving mass1 (2018/8/XX, Ushiba)
- MN moving mass2 (2018/8/XX, Ushiba)
- PF moving mass1 (2018/8/XX, Ushiba)
- PF moving mass2 (2018/8/XX, Ushiba)