= bKAGRA Phase2 =
 * Target: Joining O3 with ~10Mpc of BNC.
 * Term: 2018/5/7 ~ 2019/May? 
----
== Schedule ==
2017/8/21 updated

{{attachment:KAGRA/Commissioning/Phase2/Chief180821_Phase2_schedule.png||width=1000}}


-----
=== HPL stage ===
 * Target: High power laser
 * Term: 2018/5/7 ~ 2018/8/31


=== XA stage ===
 * Target: X arm commissioning
 * Term: 2018/9/1 ~ 2018/12?
 * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit#gid=0|Task list]]
 * Milestone
  * VIS ITMX
   * [[/CheckList/VacuumITMX|Check list]] for ITMX closing
  * Initial alignment of X arm
  * Cavity lock with IR
  * Cavity lock with green


=== YA stage ===
 * Target: Y arm commissioning
 * Term: 2019/1? ~ 2019/3?
 * Milestone
  * Replacing ETMY
  * VIS and CRY of ITMY
  * Initial alignment of Y arm
  * Cavity lock with IR
  * Cavity lock with green


=== FPMI stage ===
 * Target: FPMI commissioning
 * Term: 2019/3? ~ 2019/4?

=== RSE stage ===
 * Target: DRFPMI commissioning

=== Observation ===

 * Joinning O3 of LIGO/VIRGO