 * Schedule
 * ETMX

== 3. 当面の検討事項 ==
  * ETMX: 最新では1/26富山大着、3/16神岡着予定。
Line 17: Line 18:
== 4. Task or 検討事項 == == 3. Task or 検討事項 ==
Line 19: Line 20:
== 5. Phase2 == == 4. Phase2 ==
 * Road mapの確認
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0076/M1807641/001/kagra_ITM171215_4.pdf|Roadmap]]の中の7ページ目(case study A-3)参照。

 * Stageの定義及びエンジニアリングラン
  * Stage1: Xarm lock (~2018/10) + 1 day engineering run
  * Stage2: Corner lock (~2019/1)
  * Stage3: Yarm lock (~2019/5)
  * Stage4: FPMI lock (~2019/7) + 3 days engineering run
  * Stage5: Full configuration (~2019/9) + 3 days engineering run

1. 先週までの作業報告と今後数週間の作業予定

  • アラインメント
    • Baffle PD
    • REFL port
  • Type A
    • 1/13, 14の作業の報告
  • 1/17の12時半より真空引きの直前の打ち合わせ
    • 真空引き
    • 冷却
  • 入射パワーをどれくらい必要かを検討する。(苔山)

2. Stage 3

  • ETMX: 最新では1/26富山大着、3/16神岡着予定。

3. Task or 検討事項

4. Phase2

  • Road mapの確認
    • Roadmapの中の7ページ目(case study A-3)参照。

  • Stageの定義及びエンジニアリングラン
    • Stage1: Xarm lock (~2018/10) + 1 day engineering run
    • Stage2: Corner lock (~2019/1)
    • Stage3: Yarm lock (~2019/5)
    • Stage4: FPMI lock (~2019/7) + 3 days engineering run
    • Stage5: Full configuration (~2019/9) + 3 days engineering run