Line 15: | Line 15: |
* BF is also tuned. | * BF is also being tuned. |
Line 24: | Line 24: |
* One of the cables for picomotor was cut and broken between the connector and cable, probably due to the duct connection. * |
* One of the flat ribbon cables to picomotor was cut and broken between the connector and cable, probably due to the duct connection. |
Line 29: | Line 27: |
* X end PD will be removed. Baffle PD will be located instead. Changing PD will be done around 3/26. * Effect of Heat link to hardness of Yaw motion(Miyamoto, Ushiba) |
* X end PD was removed. Baffle PD will be located instead. Changing PD will be done around 3/26. |
Line 37: | Line 30: |
* Current temperature is ~40K. Speed of lowering temperature increased in these 3 days. | * Current temperature is 18K. Speed of lowering temperature increased in these 3 days. |
Minute of KAGRA commissioning meeting
- Date: 2018/3/13 11AM~12PM
- Attendance: Miyakawa, Aso, Izumi, Ushiba, Yamamoto, Koseyama
- eZuce: Hirose, Tomaru, Miyoki
1. Report of work of the last week and plan of work
- Alignment, ETMY: Izumi
- Tuning of ETMY is still going on. ETMY yaw motion is still too large.
- Trying feedforward, but not so effective.
- BF is also being tuned.
- Alignment to REFL port was done.
- Testing full LSC model started. It will be run at k1imc.
- RT model seems to have additional time delay ~61usec to 200usec. Unknown.
- Beam will be checked every night.
- CAL group also requires iMC in the night.
- Some of SUS, specially IMMT showed jumps several times, probably due to duct connection.
- One of the flat ribbon cables to picomotor was cut and broken between the connector and cable, probably due to the duct connection.
- Tuning of ETMY is still going on. ETMY yaw motion is still too large.
- CAL:
- X end PD was removed. Baffle PD will be located instead. Changing PD will be done around 3/26.
- Cryo:
- Current temperature is 18K. Speed of lowering temperature increased in these 3 days.
2. Schedule of ETMX installtion
- See schedule
- Check list for ETMX, Center.
- Improved point for EMTX should be shared to Vacuum team. It will be listed and shared.
- Bug list is made by izumi-kun, it will be merged to above list.
3. Tasks or discussions
Feed back to BS for MICH
- Experimental side:
- Data analysis side:
- LSC model(Michimura, Izumi)
- Same as iKAGRA or full model?
- CAL model location? which PC?
Selection of storing DAQ channel -> DGS, before phase 1
- Check the total amount.
Screens at control room -> who, when?
- Needs laser safety information.
GW alert: online alert in the control room might be prepared. -> Togoshi
4. Phase2
Others
- Next meeting: 3/13