= Minute of KAGRA commissioning meeting = ---- * Date: 2018/3/13 11AM~12PM * Attendance: Miyakawa, Aso, Izumi, Ushiba, Yamamoto, Koseyama * eZuce: Hirose, Tomaru, Miyoki, Shoda, Inoue ----- == 1. Report of work of the last week and plan of work == * Alignment, ETMY: Izumi * Tuning of ETMY is still going on. ETMY yaw motion is still too large. * Trying feedforward, but not so effective. * BF is also being tuned. * Alignment to REFL port was done. * Testing full LSC model started. It will be run at k1imc. * RT model seems to have additional time delay ~61usec to 200usec. Unknown. * Beam will be checked every night. * CAL group also requires iMC in the night. * Some of SUS, specially IMMT showed jumps several times, probably due to duct connection. * One of the flat ribbon cables to picomotor was cut and broken between the connector and cable, probably due to the duct connection. * CAL: * X end PD was removed. Baffle PD will be located instead. Changing PD will be done around 3/26. * Cryo: * Current temperature is 18K. Semi equilibrium point exist and it was fallen to the point a week before. == 2. Schedule of ETMX installtion == * See the schedule at the commissioning top page. * One missing tool was found, it takes several days, but no delay at schedule. == 3. Tasks or discussions == === Feed back to BS for MICH === * Experimental side: no matter. * Data analysis side: * LSC model(Michimura, Izumi) * Full model will be implemented at k1imc. * CAL model location? at the same k1imc, or k1test with Dolphin connection. * Selection of storing DAQ channel -> DGS, before phase 1 * Check the total amount. * Screens at control room -> who, when? * Needs laser safety information. * GW alert: online alert in the control room might be prepared. -> Togoshi == 4. Phase2 == == Others == * Frequency noise can be measured by middle lock. Large intensity noise can be a problem. * Next meeting: 3/13