Differences between revisions 3 and 4
Revision 3 as of 2018-04-03 10:53:49
Size: 1241
Comment:
Revision 4 as of 2018-04-03 10:54:19
Size: 1184
Comment:
Deletions are marked like this. Additions are marked like this.
Line 16: Line 16:
  * Mirror motion has been suppressed to ~2urad. Requirement is 1urad.
  * Beam is checked almost every night.
  * Mirror motion has been suppressed less than 2urad.

Minute of KAGRA commissioning meeting


  • Date: 2018/4/3 11AM~12PM
  • Attendance: Uchiyama, Yamamoto
    • eZuce: Miyakawa, Yamamoto(Kazuhiro), Suzuki, Hirose, Inoue


1. Report of work of the last week and plan of work

  • IFO:
  • ETMs:
    • Mirror motion has been suppressed less than 2urad.
  • Oplev:
  • CAL: Yamamoto, Yokozawa
    • Started using IMC as training of calibration.
      • Simple calibration will be implemented.
    • X end PD is removed at 3/27 today.
  • RT model
  • DAQ

2. IFO check list

  • It will be prepared soon.

3. Operation

  • Please reply accommodation mail from Uchiyama-san.
  • Think for emergency.

4. Tasks or discussions

  • DAQ fix -> Miyakawa, Yamamoto

  • Selection of full channel -> DGS Yamamoto

  • Selection of science channel -> Commissioning Izumi

  • Screens at control room
    • Sensitivity.
    • PEM.
    • Needs laser safety information.
  • GW alert: online alert in the control room might be prepared. -> Togoshi

  • Frequency noise can be measured by middle lock. Large intensity noise can be a problem.

Others

  • Next meeting: 4/10

KAGRA/Commissioning/Weekly/20180403/Minute (last edited 2018-04-03 12:05:59 by OsamuMiyakawa)