= Minute of KAGRA commissioning meeting = ---- * Date: 2018/5/1 11AM~12PM * Attendance: Miyakawa, Kokeyama, Aso, Miyoki, Ushiba, Tomaru * eZuce: Suzuki, Uchiyama, Takahaashi, Ohashi, Haino, Shoda, Nakano ----- == 1. Operation == * Going well. * Duty cycle is 80-90%. * iMC is quite stable. * DAC of PR3 was dead. That was the biggest trouble. == 2. Report of work of the last week and plan of work == * IFO, ETMs: *Izumi, Enomono * Alignment work is mainly done. 3 DOF of alignment is contolled * Typical locking time is ~several hours. Longest was 10 hours or something. * iKAGRA Guardian code was mainly reused and modified. == 3. Tasks or discussions == * 5/28 extend chief meeting for looking back phase 1. == Others == * Baffle at ETMX will extracted in the week of 5/7, and it will be black coated. * Next meeting: 5/8.