 *  * Optimization of Each DOF of VIS takes 1 day, full VIS take 22 days.
Line 37: Line 37:
 * Hammaring test of ETMY showed that something hitting.
  * Cable was well placed for ETMX. Fixing ETMY should be scheduled. (Ushiba)

Minute of KAGRA commissioning meeting


  • Date: 2018/5/8 11AM~12PM
  • Attendance: Miyakawa, Yamamoto, Aso
    • eZuce: Suzuki, Hirose, Yokozawa, Izumi, Ushiba
  • 5/28 extension meeting


1. Discussion after operation

  • IFO, ETMs: Izumi, Yamamoto
    • Well done! Duty cycle is 80-90% in 1-5days, and 15-60% in 6-9days.
    • IMC was quite stable.
    • ETMY was dominant for stability of IFO in the last 4 days.
    • Optical gain fluctuated 20~30% due to the contrast defect.
    • BS coupling between L to P and Y was sometimes dominant for the contrast.
    • Error of Sunup asymmetry was also dominant by optical gain.
  • DAQ
    • DAC of PR3 was dead. Restarting k1pr3 fixed this problem. We are not sure the cause.
    • Timing of dc0 sometimes shifted. Restart daqd of k1dc0 fixed this problem. We are not sure the cause.
    • Diaggui calculates float and sometimes coherence could not be measured.
    • We switched VIS models to 2kHz to avoid glitches.
  • Satellite box should be replaced to have more capacitance.

2. Discussion after phase1

  • ETM leak was triggered 1week delay.
    • Records of opening flange are very important.
  • Manual for VIS and clean booth should be prepared.
  • Mirror schedule should be checked frequently.
  • Optimization of Each DOF of VIS takes 1 day, full VIS take 22 days.
  • Hammaring test of ETMY showed that something hitting.
    • Cable was well placed for ETMX. Fixing ETMY should be scheduled. (Ushiba)

3. Phase 2

  • Each stage and target

3. Tasks or discussions

  • 5/28 extend chief meeting for looking back phase 1.

Others

  • Baffle at ETMX will extracted in the week of 5/7, and it will be black coated.
  • Next meeting: 5/8.

1. Discussion after the phase 1 including operation

  • IFO
    • LSC, CAL etc.
  • damping
  • DAQ
  • Cryogenic
  • Vacuum

KAGRA/Commissioning/Weekly/20180508/Minute (last edited 2018-05-08 12:20:02 by OsamuMiyakawa)