Line 38: Line 38:
 * Needs ETMX cleaning.  * Needs ETMX cleaning. (Aso, Izumi, Hirose)
Line 40: Line 40:
 * TF of ETMY BF should be measured. (Izumi)
 * Cross coupling of ETMY was large. (Izumi)
Line 44: Line 46:
     * Name of "Stage" should be replaced.

Minute of KAGRA commissioning meeting


  • Date: 2018/5/8 11AM~12PM
  • Attendance: Miyakawa, Yamamoto, Aso
    • eZuce: Suzuki, Hirose, Yokozawa, Izumi, Ushiba


1. Discussion after operation

  • IFO, ETMs: Izumi, Yamamoto
    • Well done! Duty cycle is 80-90% in 1-5days, and 15-60% in 6-9days.
    • IMC was quite stable.
    • ETMY was dominant for stability of IFO in the last 4 days.
    • Optical gain fluctuated 20~30% due to the contrast defect.
    • BS coupling between L to P and Y was sometimes dominant for the contrast.
    • Error of Sunup asymmetry was also dominant by optical gain.
  • DAQ
    • DAC of PR3 was dead. Restarting k1pr3 fixed this problem. We are not sure the cause.
    • Timing of dc0 sometimes shifted. Restart daqd of k1dc0 fixed this problem. We are not sure the cause.
    • Diaggui calculates float and sometimes coherence could not be measured.
    • We switched VIS models to 2kHz to avoid glitches.
  • Satellite box should be replaced to have more capacitance.

2. Discussion after phase1

  • ETM leak was triggered 1week delay.
    • Records of opening flange are very important.
  • Manual for VIS and clean booth should be prepared.
  • Mirror schedule should be checked frequently.
  • Optimization of Each DOF of VIS takes 1 day, full VIS take 22 days.
  • Hammaring test of ETMY showed that something hitting.
    • Cable was well placed for ETMX. Fixing ETMY should be scheduled. (Ushiba)
    • Heat link might be causes of fluctuation. It should be compared with ETMX.
  • Needs ETMX cleaning. (Aso, Izumi, Hirose)
  • TF of ETMY BF should be measured. (Izumi)
  • Cross coupling of ETMY was large. (Izumi)

3. Phase 2

  • Each stage and target
    • Name of "Stage" should be replaced.
  • 5/28 extend chief meeting for looking back phase 1.

Others

  • Next meeting: 5/15.

KAGRA/Commissioning/Weekly/20180508/Minute (last edited 2018-05-08 12:20:02 by OsamuMiyakawa)