* Attendance: Miyakawa, Uchiyama, Stefan, Mio, Yokozawa * eZuce: Izumi, Eleonora, Shoda, Mateo, Hirose, Ushiba, Enomoto |
* Attendance: Miyakawa, Uchiyama, Aso, Yamamoto, Yokozawa, Enomoto, Stefan * eZuce: Izumi, Nakano, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba, Eleonora, Shoda, Tegoshi |
Line 8: | Line 8: |
== 0. Schedule == * k1ix0 will be needed by September for NAB PD. |
|
Line 11: | Line 14: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8343|JGW-T1808343]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8343|JGW-T1808343]] * Do we need WFS?(Eleonora) -> Yes, with control system.(Izumi) * Gouy phase measurement for green is also necessary. (Akutsu) * Both mirrors are at the room temperature. (Uchiyama) * Needs preparation list. (Aso) * Loss measurement will performed mainly reflection light. (Izumi) * Simulation of loss? (Eleonora) -> Hirose, Hiro Yamamoto * Camera view? (Stefan) -> PCal camera, transmitted camera * Which port will be used for locking? (Miyakawa) -> REFL port |
Line 15: | Line 28: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5055]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5124]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5126]] |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5055]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5124]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5126]] * Non-stational noise happens but it is not related water cooler. * This RIN level cannot reach shotnoise level with the first ISS loop. Current noise is 2 orders lager than NPRO noise. Needs 2nd loop to reach design level. |
Line 25: | Line 42: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5155]] | * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5155]] * MATSUSADA HV driver has 10uV/rHz, quite high. * Slow output can be used as offset, and 2nd EXC point will be used as input. * LIGO is not using temperature controller. (Stefan) |
Minute of KAGRA commissioning meeting
- Date: 2018/6/5 11AM~12PM
- Attendance: Miyakawa, Uchiyama, Aso, Yamamoto, Yokozawa, Enomoto, Stefan
- eZuce: Izumi, Nakano, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba, Eleonora, Shoda, Tegoshi
0. Schedule
- k1ix0 will be needed by September for NAB PD.
1. X arm commissioning
Do we need WFS?(Eleonora) -> Yes, with control system.(Izumi)
- Gouy phase measurement for green is also necessary. (Akutsu)
- Both mirrors are at the room temperature. (Uchiyama)
- Needs preparation list. (Aso)
- Loss measurement will performed mainly reflection light. (Izumi)
Simulation of loss? (Eleonora) -> Hirose, Hiro Yamamoto
Camera view? (Stefan) -> PCal camera, transmitted camera
Which port will be used for locking? (Miyakawa) -> REFL port
2. New 40 W laser
- RIN measurement
- Non-stational noise happens but it is not related water cooler.
- This RIN level cannot reach shotnoise level with the first ISS loop. Current noise is 2 orders lager than NPRO noise. Needs 2nd loop to reach design level.
- Beam profile
3. PMC electronic hack
- MATSUSADA HV driver has 10uV/rHz, quite high.
- Slow output can be used as offset, and 2nd EXC point will be used as input.
- LIGO is not using temperature controller. (Stefan)
Others
- Next meeting: 5/29.