Differences between revisions 2 and 3
Revision 2 as of 2018-06-05 10:49:12
Size: 974
Comment:
Revision 3 as of 2018-06-05 11:05:54
Size: 983
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * eZuce: Izumi, Nakano, Stefan, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba   * eZuce: Izumi, Nakano, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba, Eleonora, Shoda

Minute of KAGRA commissioning meeting


  • Date: 2018/6/5 11AM~12PM
  • Attendance: Miyakawa, Uchiyama, Aso, Yamamoto, Yokozawa, Enomoto, Stefan
    • eZuce: Izumi, Nakano, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba, Eleonora, Shoda


0. Schedule

  • k1ix0 will be needed by September for NAB PD.

1. X arm commissioning

2. New 40 W laser

3. PMC electronic hack

Others

  • Next meeting: 5/29.

KAGRA/Commissioning/Weekly/20180605/Minute (last edited 2018-06-05 12:04:48 by OsamuMiyakawa)