Minute of KAGRA commissioning meeting


  • Date: 2018/7/24 11AM~12PM
  • Attendance: Miyakawa, Aso, Enomoto, Yokozawa, Kozakai
    • eZuce: Miyoki, Suzuki, Nakano, Shoda, Ushiba, Yamamoto, Kimura, Uchiyama


LAS (Nakano)

  • 40W laser started working on last Friday.
    • Limite 1W will be used to alignment or so.
  • Remote desktop will be installed on Windows PC for 40W laser control.
  • Monitor of laser power should be displayed on door or something.

PSL, IOO

  • MZ of single arm mode matching is much better now. No Lager-Gaussian is seen.
    • MZ contrast is 99.4% and 96.9%. Second one has 3m arm length difference.
    • Lock wil be tried soon. Common mode servo will be used to control MZ.
  • RAM(residual amplitude monitor) monitor will be installed.
  • ISS TF model and measurement were done. Model still does not have phase delay at high frequency.
  • RIN is limited by PD dark noise up to 1kHz. Shotnoise is almost comparable.
    • UGF is currently 10kHz. Above 1kHz, suppression is not enough. It will be limited to 50kHz max in future by a commercial AOM driver of speed of variable attenuator..

Check list for IXC

  • Meeting will be assigned on one of 8/15,16,17.
  • WAB, NAB are the additional items.
  • Mirror position should be in the item list.
  • WAB PD will be installed at the sometime.
  • The number of opening flange should be minimized. It must be listed up.
  • Oplev of ITMX will be installed.
  • Safety for high power laser must be considered.

ETMX (Miyamoto)

  • Oplev power goes down with switch of cryostat.
  • Also ETMX QPD shows 1/10 or lower power in 10 hour without relationship of switch of cryostat. One of the viewport looks dewed.
  • One of the motor seemed to be stuck.
  • F2 of ETMX fell bistable point, and it is stuck.

DGS

rack cleaning

  • BS is almost done.
  • PEM meeting will be held 8/1 6pm.

Others

  • Next meeting: 8/7.