2018/8/21 Commissioning meeting topics
- Daily meeting
- Task check for IXC installation and closing to vacuum
- the readiness for the X arm commissioning.
- Initial alignment
- Laser, PSL, IOO report
Status of ETMX -> Miyamoto
PEM -> Yokozawa
- Satellite amplifier