== 2018/8/28 Commissioning meeting topics ==

 * Daily meeting
 * Night work
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8720|JGW-E1808720]]
 * Task check for IXC installation and closing to vacuum
  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX|Check list]]

 * Readiness for the X arm commissioning.
  * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

 * Initial alignment
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8462|JGW-G1808462]]

----
   * Laser, PSL, IOO report
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5892]]: PMC
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5894]]: FSS

 * ETMX damping
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5899]]
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5906]]

 * Satellite amplifier
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8691|JGW-T1808691]]: TF at low frequency has 30db bump.

 * DGS
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5887]]

 * Magnetic field measurement at IXC
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5817]]