Minute of KAGRA commissioning meeting


  • Date: 2018/10/2 11AM~12PM
  • Attendance: Miyakawa, Yamamoto, Yokozawa, Kozakai, Kokeyama
    • Zoom: Ushiba, Suzuki, Enomoto


X arm alignment

  • Beam is returned back to central area from ETMX!
  • Waiting for ITMX fixed.
  • Oplev moved somehow. It is not clear why.

Trouble of ITMX

Trouble of PR2 and PR3

IOO

  • Seems to be stable for PMC, IMC.
  • 5W will be out in the PSL.

Picomotor

  • New driver seemed to be not working. Miyo-kun tried it in other network, the it worked.
    • Trouble might be network traffic in kAGRA control.

DGS

  • EPICS gateway has been implemented. Network traffic should be much smaller now (~1/10).
  • Still not perfect. Needs more tuning.

CAL

  • Installation of periscope.

Others

  • Next meeting: 10/9.