Line 10: Line 10:

 * 11/6 AM or PM for 30min : Inspection for ETMX cleaning
 * 12/10 or 11 ETMX cleaning
 * 11/5-end of Nov.: IYA root will be closed.
 * 11/6: AM or PM for 30min : Inspection for ETMX cleaning
 * 12/10 or 11: ETMX cleaning
Line 14: Line 14:
 * Assignment of tuning for suspensions.
Line 17: Line 18:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6697]]: damping loop engaged   * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6697]]: OLTF

2018/10/30 Commissioning meeting topics


  • 11/5-end of Nov.: IYA root will be closed.
  • 11/6: AM or PM for 30min : Inspection for ETMX cleaning
  • 12/10 or 11: ETMX cleaning
  • MZ work needs stopping IR in the daytime; ~10/31 ok, 11/1~11/31?
  • Assignment of tuning for suspensions.