= Minute of KAGRA commissioning meeting =
----

 * Date: 2018/10/30 11AM~12PM
 * Attendance: Miyakawa, Oshino
  * Zoom: Ushiba, Aso, Nakano, Izumi, Somiya

-----
=== Schedule ===
 * MZ work will be done during daytime until 11/26.
 * Y arm alignment will start from 11/26 to 12/9 with a parallel work on X arm commissioning.

----
 * X arm lock
  * PR3 had better motion. Oplev has some trouble on cover.
  * Currently locking time (~1hour) might be limited by iMC lock.

 * Laser, PSL, IOO report
  * MC lock is lost every 2-3hours.
  * Accelerometers see some disturbance.

 * OMC installation
  * Locked by independent laser using one PD by dither method.
  * Congratulation!
  * LIGO has 64kHz loop on PI for beacon. It is not yet sure that the beacon is needed in KAGRA.

 * DGS
  * Scheduling for maintenance time on Wednesday morning. DAC and ITMY will be stopped.

 * NAB PD
  * Satellite box arrived.

== Others ==
 
 * Next meeting: 11/13.