Line 14: | Line 14: |
* 11/16: PM for 30min : Inspection for ETMX cleaning | |
Line 16: | Line 15: |
* 11/26~12/9 Daytime: Y arm alignment from BS to ETMY using IR beam. | * 11/23-25: Line injection * 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam. |
Line 18: | Line 18: |
* Beam alignment actually starts after the installation of NAB. It will take several days. * Green from SR2 will be available after 12/9. |
* Beam alignment will actually start after the installation of EYA NAB. It will take several days. * Green from SR2 will be available after 12/9, so we need to align Y arm using IR only. |
Line 31: | Line 31: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6906]]: 2 hour lock * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6940]]: Frequency noise CARMed down |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6994]]: REFL table. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7011]]: CARM fast path. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7022]]: CARM fast path. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7030]]: Offset fluctuation between Green and IR? * Y arm alignment * Optical table |
Line 35: | Line 40: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6874]]: Lock-loss investigation of the IMC * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6884]]: Fix FSS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6948]]: The PSL was operated with the full power of the fiber amp.!! |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6991]]: PMC UGF. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7010]]: FSS and IMC UGF. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7021]]: Power budget. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6986]]: ISS noise. |
Line 39: | Line 45: |
* CAL * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6843]]: calibration line injection test * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6848]]: calibration line injection test |
* AOS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6990]]: Green ghost. |
2018/11/20 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- Every Wednesday morning: Maintenance
- 11/5-end of Nov.: Route to IYA is closed.
- Needs time sharing with MZ in the daytime until 11/26.
- 11/23-25: Line injection
- 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
- Members: Enomoto, Miyazaki, Yokogawa, Sugimoto
- Beam alignment will actually start after the installation of EYA NAB. It will take several days.
- Green from SR2 will be available after 12/9, so we need to align Y arm using IR only.
- Needs help for Y arm alignment.
- 12/10 or 11: ETMX cleaning
Discussion
- We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
- Needs re-scheduling for the X arm commissionig?
- X arm lock
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6994: REFL table.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7011: CARM fast path.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7022: CARM fast path.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7030: Offset fluctuation between Green and IR?
- Y arm alignment
- Optical table
- Laser, PSL, IOO report
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7010: FSS and IMC UGF.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7021: Power budget.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6986: ISS noise.
- AOS
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6990: Green ghost.