== 2018/11/20 Commissioning meeting topics ==

 * Assignment of staffs for night work
  * [[https://teamup.com/kswnmta8p18h6u1uab]]

 * Readiness for the X arm commissioning.
  * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]]

----
=== Schedule ===

 * Every Wednesday morning: Maintenance
 * 11/5-end of Nov.: Route to IYA is closed.
 * Needs time sharing with MZ in the daytime until 11/26.
 * 11/23-25: Line injection
 * 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
  * Members: Enomoto, Miyazaki, Yokogawa, Sugimoto
  * Beam alignment will actually start after the installation of EYA NAB. It will take several days.
  * Green from SR2 will be available after 12/9, so we need to align Y arm using IR only.
  * Needs help for Y arm alignment.
 * 12/10 or 11: ETMX cleaning

----
=== Discussion ===

 * We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
 * Needs re-scheduling for the X arm commissionig?

----
 * X arm lock
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6994]]: REFL table.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7011]]: CARM fast path.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7022]]: CARM fast path.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7030]]: Offset fluctuation between Green and IR?

 * Y arm alignment
  * Optical table

 * Laser, PSL, IOO report
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6991]]: PMC UGF.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7010]]: FSS and IMC UGF.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7021]]: Power budget.
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6986]]: ISS noise.


 * AOS
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6990]]: Green ghost.