* Needs time sharing with MZ in the daytime until 11/26. * 11/23-25: Line injection |
|
Line 17: | Line 14: |
* Members: Enomoto, Miyazaki, Yokogawa, Sugimoto | * 11/28 evening: First contact remove. It might be postponed. |
Line 19: | Line 16: |
* Green from SR2 will be available after 12/9, so we need to align Y arm using IR only. * Needs help for Y arm alignment. |
* BS is sitting on the plate due to the temperature change. * Green from SR2 will be available in January, so we need to align Y arm using IR only. * QPD or PDA at EYA. Cable is already laid. |
Line 22: | Line 20: |
* Week of 12/10: Night work ok. * Week of 12/17~: No night work. |
|
Line 23: | Line 23: |
* Extension: 12/10-1/6. * Week of 12/10: Night work ok. * Week of 12/17~ : No night work. |
* New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed. [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9311|Other list by Saito]]. * Possible extension date: 12/10-1/6. * 1/6: End of X arm commissioning -> Open chambers. * Week of 1/7~: no beam in the daytime * 2/18~ Y arm commissioning |
Line 32: | Line 33: |
* Needs re-scheduling for the X arm commissionig? | |
Line 36: | Line 36: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6994]]: REFL table. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7011]]: CARM fast path. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7022]]: CARM fast path. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7030]]: Offset fluctuation between Green and IR? |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7098]]: Noise injection at POP. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7107]]: Noise injection at POP. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7115]]: Noise injection at POP. |
Line 45: | Line 44: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6991]]: PMC UGF. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7010]]: FSS and IMC UGF. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7021]]: Power budget. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6986]]: ISS noise. |
|
Line 50: | Line 45: |
* AOS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6990]]: Green ghost. |
* PEM * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7116]]: Earth quake. |
2018/11/27 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- Every Wednesday morning: Maintenance
- 11/5-end of Nov.: Route to IYA is closed.
- 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
- 11/28 evening: First contact remove. It might be postponed.
- Beam alignment will actually start after the installation of EYA NAB. It will take several days.
- BS is sitting on the plate due to the temperature change.
- Green from SR2 will be available in January, so we need to align Y arm using IR only.
- QPD or PDA at EYA. Cable is already laid.
- 12/10 or 11: ETMX cleaning
- Week of 12/10: Night work ok.
- Week of 12/17~: No night work.
New schedule Plan B is proposed. Other list by Saito.
- Possible extension date: 12/10-1/6.
1/6: End of X arm commissioning -> Open chambers.
- Week of 1/7~: no beam in the daytime
- 2/18~ Y arm commissioning
Discussion
- We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
- X arm lock
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7098: Noise injection at POP.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7107: Noise injection at POP.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7115: Noise injection at POP.
- Y arm alignment
- Optical table
- Laser, PSL, IOO report
- PEM
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7116: Earth quake.