2018/11/27 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance
  • 11/5-end of Nov.: Route to IYA is closed.
  • Needs time sharing with MZ in the daytime until 11/26.
  • 11/23-25: Line injection
  • 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
    • Members: Enomoto, Miyazaki, Yokogawa, Sugimoto
    • Beam alignment will actually start after the installation of EYA NAB. It will take several days.
    • Green from SR2 will be available after 12/9, so we need to align Y arm using IR only.
    • Needs help for Y arm alignment.
  • 12/10 or 11: ETMX cleaning
  • 11/26: Extended chief meeting require some explanation of current status.
  • Deadline of decision where postponement or not: at least after 11/26.
  • Possible extension date: 12/10-1/6.
  • Week of 12/10: Night work ok.
  • Week of 12/17~ : No night work.


Discussion

  • We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
  • Needs re-scheduling for the X arm commissionig?