Line 11: Line 11:
 * New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed.
Line 18: Line 17:

 * 11/26: Extended chief meeting require some explanation of current status.
 * Deadline of decision where postponement or not: at least after 11/26.
 * Possible extension date: 12/10-1/6.
Line 24: Line 19:
 * End of X arm commissioning: 1/6. -> Open chambers
 * Week of 1/7~: no beam in the daytime
 * 2/18~ Y arm commissioning

 * New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed.
  * Possible extension date: 12/10-1/6.
 
* End of X arm commissioning: 1/6. -> Open chambers
  * Week of 1/7~: no beam in the daytime
  * 2/18~ Y arm commissioning

2018/11/27 Commissioning meeting topics


Schedule

  • Every Wednesday morning: Maintenance
  • 11/5-end of Nov.: Route to IYA is closed.
  • 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
    • Beam alignment will actually start after the installation of EYA NAB. It will take several days.
    • Green from SR2 will be available after 12/9, so we need to align Y arm using IR only.
  • 12/10 or 11: ETMX cleaning
  • Week of 12/10: Night work ok.
  • Week of 12/17~: No night work.
  • New schedule Plan B is proposed.

    • Possible extension date: 12/10-1/6.
    • End of X arm commissioning: 1/6. -> Open chambers

    • Week of 1/7~: no beam in the daytime
    • 2/18~ Y arm commissioning


Discussion

  • We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
  • Needs re-scheduling for the X arm commissionig?