2140
Comment:
|
2096
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
* New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed. | |
Line 18: | Line 17: |
* 11/26: Extended chief meeting require some explanation of current status. * Deadline of decision where postponement or not: at least after 11/26. * Possible extension date: 12/10-1/6. |
|
Line 24: | Line 19: |
* End of X arm commissioning: 1/6. -> Open chambers * Week of 1/7~: no beam in the daytime * 2/18~ Y arm commissioning |
* New schedule [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9310|Plan B]] is proposed. [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9311|Other list by Saito]]. * Possible extension date: 12/10-1/6. * 1/6: End of X arm commissioning -> Open chambers. * Week of 1/7~: no beam in the daytime * 2/18~ Y arm commissioning |
2018/11/27 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- Every Wednesday morning: Maintenance
- 11/5-end of Nov.: Route to IYA is closed.
- 11/26~12/9: Daytime: Y arm alignment from BS to ETMY using IR beam.
- Beam alignment will actually start after the installation of EYA NAB. It will take several days.
- Green from SR2 will be available after 12/9, so we need to align Y arm using IR only.
- 12/10 or 11: ETMX cleaning
- Week of 12/10: Night work ok.
- Week of 12/17~: No night work.
New schedule Plan B is proposed. Other list by Saito.
- Possible extension date: 12/10-1/6.
1/6: End of X arm commissioning -> Open chambers.
- Week of 1/7~: no beam in the daytime
- 2/18~ Y arm commissioning
Discussion
- We learned we need to monitor VIS motion when pump down. We may need also some monitors VIS motion when venting.
- Needs re-scheduling for the X arm commissionig?
- X arm lock
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6994: REFL table.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7011: CARM fast path.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7022: CARM fast path.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7030: Offset fluctuation between Green and IR?
- Y arm alignment
- Optical table
- Laser, PSL, IOO report
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7010: FSS and IMC UGF.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=7021: Power budget.
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6986: ISS noise.
- AOS
http://klog.icrr.u-tokyo.ac.jp/osl/?r=6990: Green ghost.