Line 48: Line 48:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7339]]: noise investigation for ALS X
Line 52: Line 51:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7404]]: Set up for ALSY system
Line 55: Line 53:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7348]]: Drift of the vertical GAS Filter
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7377]]: PRM, BFLVDT-Glitch
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7389]]: ETMY, GAS-STM...?
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7395]]: first version of the inertial damping for the IP of the ITMX
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7406]]: IP-stage drift and compensation
Line 65: Line 58:
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9523]]: Debuggin the scattered light problem.
Line 68: Line 60:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7251]]:SDF
Line 71: Line 62:
  * Any trouble for updating RCG?

2018/12/25 Commissioning meeting topics


Schedule

  • 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
    • 1/4-6: Removal of first contact of ETMY
  • 12/29,30: line injection.
  • 1/6: End of X arm commissioning.
  • 1/7~ : High power shutter installation.
  • 1/7~ : Opening EXC chamber.
  • 1/7~ : Hight check for VIS systems.
  • 1/17~ : Y arm alignment from BS to ETMY using IR beam.
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
    • 12/18-28: CAL work at EXA


  • X commissioning
  • Y arm
  • VIS
  • Laser, PSL, IOO report
  • PCAL
  • PEM
  • DGS