Differences between revisions 1 and 6 (spanning 5 versions)
Revision 1 as of 2018-12-25 10:16:46
Size: 2235
Comment:
Revision 6 as of 2018-12-25 11:20:05
Size: 1673
Comment:
Deletions are marked like this. Additions are marked like this.
Line 14: Line 14:
 * 1/4 Camera moves to ETMY.
Line 15: Line 16:
 * 1/7~ : High power shutter installation.
 * 1/7~ : Opening EXC chamber.
* 1/7~ : Hight check for VIS systems.
 * 1/17~ : Y arm alignment from BS to ETMY using IR beam.
 * 1/7~ : Opening chambers.
 
* 1/7~ : High power beam dump installation.
  * 1/14~18 : Hight check for VIS systems.
  * 1/7~11 : BS tuning
Line 48: Line 48:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7339]]: noise investigation for ALS X


 * Y arm
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7404]]: Set up for ALSY system

 * VIS
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7348]]: Drift of the vertical GAS Filter
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7377]]: PRM, BFLVDT-Glitch
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7389]]: ETMY, GAS-STM...?
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7395]]: first version of the inertial damping for the IP of the ITMX
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7406]]: IP-stage drift and compensation
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7425]]: ALS noise investigation: ADC noise and re-measurement of VCO noise
Line 62: Line 51:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7451]]: Installation of High power beam shutter
Line 63: Line 53:

 * PCAL
  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9523]]: Debuggin the scattered light problem.

 * PEM
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7251]]:SDF

 * DGS
  * Any trouble for updating RCG?
 * AOS
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7469]]: Evacuating the EXT chamber

2018/12/25 Commissioning meeting topics


Schedule

  • 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
    • 1/4-6: Removal of first contact of ETMY
  • 12/29,30: line injection.
  • 1/4 Camera moves to ETMY.
  • 1/6: End of X arm commissioning.
  • 1/7~ : Opening chambers.
    • 1/7~ : High power beam dump installation.
    • 1/14~18 : Hight check for VIS systems.
    • 1/7~11 : BS tuning
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
    • 12/18-28: CAL work at EXA