Differences between revisions 2 and 3
Revision 2 as of 2018-12-25 10:17:23
Size: 1430
Comment:
Revision 3 as of 2018-12-25 10:43:00
Size: 1395
Comment:
Deletions are marked like this. Additions are marked like this.
Line 15: Line 15:
 * 1/7~ : High power shutter installation.
 * 1/7~ : Opening EXC chamber.
* 1/7~ : Hight check for VIS systems.
 * 1/17~ : Y arm alignment from BS to ETMY using IR beam.
 * 1/7~ : Opening chambers.
 
* 1/7~ : High power shutter installation.
  * 1/14~18 : Hight check for VIS systems.
  * 1/7~11 : BS tuning

2018/12/25 Commissioning meeting topics


Schedule

  • 12/18-19 or 1/4-6: Removal of aluminum foil for WAB at EYC.
    • 1/4-6: Removal of first contact of ETMY
  • 12/29,30: line injection.
  • 1/6: End of X arm commissioning.
  • 1/7~ : Opening chambers.
    • 1/7~ : High power shutter installation.
    • 1/14~18 : Hight check for VIS systems.
    • 1/7~11 : BS tuning
  • beam alignment:
    • 1/7~: Opening IMC Chamber.
      • IMC beam alignment in air: 1/11-14
      • IMC lock recover in vacuum: 1/16
      • IMC to ETMX: 1/17-21
    • BS to ETMY: 1/17-21
    • ITMY to REFL: 1/21-22
    • ITMY to SRM: 1/22-23
    • ITMY to OMC: 1/23-25
    • ITMX to OMC: 1/23-25
    • POS to ETMY(Green laser): 1/23-24
    • ETMY to POS(Green laser): 1/24-25
    • ETMX to ITMX: 2/11-22
  • 2/4~ DRMI Y arm commissioning
  • 2/18~ Y arm commissioning
  • 3/18~ FPMI commissioning


Discussion

  • Time sharing without night work time in the mine, specially CAL, VIS and commissioning.
    • 12/18-28: CAL work at EXA


  • X commissioning
  • Y arm
  • VIS
  • Laser, PSL, IOO report
  • PCAL
  • PEM
  • DGS

KAGRA/Commissioning/Weekly/20181225/Agenda (last edited 2018-12-25 11:20:05 by OsamuMiyakawa)