Size: 2922
Comment:
|
← Revision 5 as of 2019-01-22 14:57:19 ⇥
Size: 1443
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
* 1/4 Camera moves to ETMY. * 1/6: End of X arm commissioning. * 1/7-15: Laser stop in the laboratory area. * 1/7: Removal of aluminum foil for WAB at EYC. * 1/7?: Removal of first contact of ETMY * 1/7~ : Opening chambers. * 1/7~ : High power beam dump installation. * 1/14~18 : Hight check for VIS systems. * 1/7~11 : BS tuning * 1/9? or later: EYC pumping down |
|
Line 48: | Line 38: |
* 2/22?~: Periscope installation * 3/11- Xend WAB |
* Periscope installation * 3/11,12 Xend WAB * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test |
Line 66: | Line 59: |
* X commissioning * Some noise improvement: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7546]]: modulation index, whitening * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7553]]: filsters off * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7561]]: PR2 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7562]]: ALS Noise Budget * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7571]]: ALS Noise Budget * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7499]]: Dither Alignment Control * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7507]]: Dither Alignment Control * VIS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7573]]: TF of type A * Laser, PSL, IOO report * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7572]]: MC cavity pole * AOS * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7502]]: Beam profile measurement on the TMSX table * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7574]]: Beam profile measurement on the TMSX table * Y arm preparation: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7538]]: Green beam for Y arm was coupled to the optical fiber * DGS: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7534]]: TYPE-A model downsampling |
2019/1/22 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- beam alignment:
- 1/7~: Opening IMC Chamber.
- IMC beam alignment in air: 1/11-14
- IMC lock recover in vacuum: 1/16
- IMC to ETMX: 1/17-21
- BS to ETMY: 1/17-21
- ITMY to REFL: 1/21-22
- ITMY to SRM: 1/22-23
- ITMY to OMC: 1/23-25
- ITMX to OMC: 1/23-25
- POS to ETMY(Green laser): 1/23-24
- ETMY to POS(Green laser): 1/24-25
1/27: end of alignment up to SRs
- 2/18-20 EXC door close
- ETMX to ITMX: 2/21-22
- 1/7~: Opening IMC Chamber.
- Yend
- 1/25-2/22: Yend Pcal finalization
- 2/25-3/4: Yend WAB
- 3/8~ : Yend pumpdown 3/8~
- 3/11,12: leak test
- Xend
- 2/22-3/10: Xend Pcal finalization
- 2/11-2/22: Xend NAB installation
- Periscope installation
- 3/11,12 Xend WAB
- 3/19,20, Heatlink etc.
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work start
- 2/4(no delay)-3/8 DRMI commissioning
- 3/11(3weeks delay)-4/5 Y arm commissioning
- 3/25(1week delay)-4/5 FPMI commissioning
Discussion
- X amr commissioning summary
- schedule for Y arm alignment, etc.
- Modulation by Mach-Zehnder