== 2019/1/29 Commissioning meeting topics == * Assignment of staffs for night work * [[https://teamup.com/kswnmta8p18h6u1uab]] * Readiness for the X arm commissioning. * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] ---- === Schedule === * Schedule * Current status as of 1/22: IR and Green reached X end PD. * --(1/22 Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/22 or 23 Surface inspection for SR mirrors.)-- * --(1/24-25 Cleaning HR of SR3, SRM.)-- * --(1/23 BS is aligned to Y-end PD by IR.)-- * --(1/24-25 ITMY is aligned to REFL by IR.)-- * --(1/24-25 ITMX is aligned to REFL by IR.)-- * --(1/24-25 Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29 SR3 is aligned to SR2 center by IR.)-- * 1/30 --(Green beam is injected from SR2 AR surface)-- to Y end PD. * 1/31-2/1 Removing bellows at PR and SR area. * 1/31-2/1 Cleaning HR of PR3 and HR, AR of SR2 * 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/4-8 Alignment of ETMY -> POS by Green * 2/12-15 Closing door for central area, pumping down * needs drift monitor for VIS * Yend (Not yet determined due to the schedule change above) * --(1/25-2/22: Yend Pcal finalization)-- * 2/25-3/4: Yend WAB * 3/8~ : Yend pumpdown 3/8~ * 3/11,12: leak test * Xend (Not yet determined due to the schedule change above) * 2/22-3/10: Xend Pcal finalization * 2/11-2/22: Xend NAB installation * Periscope installation * 3/11,12 Xend WAB * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work start * 2/18(no delay)-3/8 DRMI commissioning * 3/11(3weeks delay)-4/5 Y arm commissioning * 3/25(1week delay)-4/5 FPMI commissioning ---- === Discussion === * ----