2019/1/29 Commissioning meeting topics
- Assignment of staffs for night work
- Readiness for the X arm commissioning.
Schedule
- beam alignment:
- Current status as of 1/22: IR and Green reached X end PD.
- 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.
- 1/22 or 23 Surface inspection for SR mirrors.
- 1/23-25 Cleaning HR of SR2.
- 1/23 BS will be aligned to Y-end PD by IR.
- 1/24-25 ITMX will be aligned to REFL by IR.
- 1/24-25 ITMY will be aligned to REFL by IR.
- 1/26 Beam position of IR at SR3 will be confirmed how far from the center.
- 1/28-29 SR3 will be aligned to SR2 center by IR.
- 1/30 Green beam will be injected from SR2 AR surface to Y end PD.
- 1/31-2/1 Removing bellows at PR and SR area.
- 1/31-2/1 Cleaning HR of PR3 and AR of SR2
2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR
2/4-8 Alignment of ETMY -> POS by Green
- 2/12-15 Closing door for central area, pumping down
- needs drift monitor for VIS
- Yend (Not yet determined due to the schedule change above)
- 1/25-2/22: Yend Pcal finalization
- 2/25-3/4: Yend WAB
- 3/8~ : Yend pumpdown 3/8~
- 3/11,12: leak test
- Xend (Not yet determined due to the schedule change above)
- 2/22-3/10: Xend Pcal finalization
- 2/11-2/22: Xend NAB installation
- Periscope installation
- 3/11,12 Xend WAB
- 3/19,20, Heatlink etc.
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work start
- 2/18(no delay)-3/8 DRMI commissioning
- 3/11(3weeks delay)-4/5 Y arm commissioning
- 3/25(1week delay)-4/5 FPMI commissioning
Discussion