== 2019/2/5 Commissioning meeting topics == * Assignment of staffs for night work * [[https://teamup.com/kswnmta8p18h6u1uab]] * Readiness for the X arm commissioning. * [[https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing]] ---- === Schedule === * Schedule * Current status as of 1/22: IR and Green reached X end PD. * --(1/22: Surface inspection for PR mirrors.)-- Cleaning will be done after 1/31. * --(1/23: Surface inspection for SR mirrors.)-- * --(1/24-25: Cleaning HR of SR3, SRM.)-- * --(1/23: BS is aligned to Y-end PD by IR.)-- * --(1/27: ITMY is aligned to REFL by IR.)-- * --(1/27: ITMX is aligned to REFL by IR.)-- * --(1/27: Beam position of IR at SR3 is confirmed how far from the center.)-- * --(1/28-29: SR3 is aligned to SR2 center by IR.)-- * --(1/28: Alignment of SR2 -> SRM by IR.)-- * --(1/29: Green beam is injected from SR2 AR surface to Y end PD.)-- * --(1/31: Removing bellows at PR and SR area.)-- * --(1/31-2/1: Cleaning HR of PR3 and HR, AR of SR2)-- * 2/4-8: SRM alignment, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR * 2/4-8: Alignment of ETMY -> POS by Green * 2/12-15: Closing door for central area, pumping down * needs drift monitor for VIS * Yend (Not yet determined due to the schedule change above) * 1/25-2/22: Yend Pcal finalization * 2/25-3/4: Yend WAB * 3/8~ : Yend pumpdown 3/8~ * 3/11,12: leak test * Xend (Not yet determined due to the schedule change above) * 2/22-3/10: Xend Pcal finalization * 2/11-2/22: Xend NAB installation * Periscope installation * 3/11,12 Xend WAB * 3/19,20, Heatlink etc. * 3/22 Pumping down * Leak test * 3/11~ : Night work start * 2/18(no delay)-3/8 DRMI commissioning * 3/11(3weeks delay)-4/5 Y arm commissioning * 3/25(1week delay)-4/5 FPMI commissioning ---- === Discussion === * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7931]]: Mirror inspection and cleaning. * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9658|JGW-G1909658]]: new application of photon calibrator for commissioning and observation. * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7943]]: SRM * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=7942]]: High power test ----