2019/3/5 Commissioning meeting topics


Schedule

  • Center
    • 2/26-27: Venting

    • 2/28-3/5: Fixing PRMs and SRMs
    • 3/2-5: Re-alignment
    • 3/6-7: Closing
  • Yend
    • 1/25-2/20: Yend Pcal finalization

    • 2/25-3/4: Yend WAB finalization
    • 3/5-6: Closing
    • 3/6~ : Yend pumpdown 3/6~
      • 3/7,8: leak test
  • Xend
    • 2/11-2/14: Xend NAB installation

    • 2/21: Removing FC, Payload release

      • 2/27: ETMX release

    • 2/23-3/10: Xend Pcal finalization 1
      • Periscope installation
      • Beam position by IR and Green
    • 3/5: ETMX aligned
    • 3/5-3/10: Xend Pcal finalization 2
    • 3/11,12 Xend WAB finalization
    • 3/19,20, Heatlink etc.
    • 3/22 Pumping down
      • Leak test
  • 3/11~ : Night work starts
  • 2/18-3/22 DRMI commissioning
  • 3/11-4/5 Y arm commissioning
  • 3/25-4/5 FPMI commissioning


Discussion

  • Plan of engineering runs with FPMI configuration in May.
  • Health check and maintenance for VIS