Size: 1895
Comment:
|
← Revision 12 as of 2019-03-05 13:25:15 ⇥
Size: 2232
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 12: | Line 12: |
* 2/28-3/5: Fixing PRMs and SRMs | * 2/28-3/6: Health check and maintenance for VIS * PRM: One flag was dropped. -> leave it * PRM: Misalignment does not reach where beam hits damper. -> 3/4-5 * PR3: range -> incline by 20-30mrad at mirror because of bistable. -> 3/5-6 * BS: Yaw offset adjustment by hand. -> 3/5-6 |
Line 14: | Line 19: |
* 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water. | |
Line 19: | Line 25: |
* 3/5: EYA remaining works by Enomoto, Inoue. | |
Line 20: | Line 27: |
* 3/5-6: Closing * 3/6~ : Yend pumpdown 3/6~ |
* 3/5: AOS EY and EX(if they have time) work. * 3/6: Y end closing (no laser hazard at least in the morning) * Alignment to ETMX by 3/7 morning * 3/7: Y end pump down |
Line 31: | Line 40: |
* 3/5: ETMX aligned | * 3/5 and 3/11~: ETMX seems to be hitting somewhere? Tuning was not enough(by Takahashi). * 3/5: ETMX aligned with oplev accuracy |
Line 33: | Line 43: |
* 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. |
* 3/5: AOS EY and EX(if they have time) work. * 3/6: Green X alignment (no IR), and no hazard at Y end. * 3/9-10(fastest, then 3/23): Pcal finalization * 3/11, 18,19: Xend WAB finalization. * 3/19: Heatlink etc. * 3/19: ETMX finalization by Takahashi * 3/21 closing |
Line 38: | Line 53: |
* 3/11~ : Night work starts | * 3/11~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. |
Line 50: | Line 66: |
* Health check and maintenance for VIS * PRM: One flag was dropped. -> leave it * PRM: Misalignment does not reach where beam hits damper. -> 3/4-5 * PR3: range -> incline by 20-30mrad at mirror because of bistable. -> 3/5-6 * BS: Yaw offset adjustment by hand. -> 3/5-6 * 3/6: Green X alignment, and no hazard at Y end. * 3/5: EYA remaining works by Enomoto, Inoue. * 3/6: Yend closing (no laser hazard at least morning) * Alignment to ETMX by 3/7 morning * 3/7: Center closing * 3/9-10(fastest, then 3/23): Pcal finalization * ETMX: It seems to be hitting somewhere? -> 3/5 and 3/11~. It can be in parallel with WAB finalization at 3/11-12. * 3/21-22: X end pumpdown. |
* Drift monitor for Type A with low temperature. |
2019/3/5 Commissioning meeting topics
- Assignment of staffs
Schedule
- Center
2/26-27: Venting
- 2/28-3/6: Health check and maintenance for VIS
PRM: One flag was dropped. -> leave it
PRM: Misalignment does not reach where beam hits damper. -> 3/4-5
PR3: range -> incline by 20-30mrad at mirror because of bistable. -> 3/5-6
BS: Yaw offset adjustment by hand. -> 3/5-6
- 3/2-5: Re-alignment
- 3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.
- 3/7: Closing
- 3/8: pump down
- Yend
1/25-2/20: Yend Pcal finalization
- 3/5: EYA remaining works by Enomoto, Inoue.
- 2/25-3/4: Yend WAB finalization
- 3/5: AOS EY and EX(if they have time) work.
- 3/6: Y end closing (no laser hazard at least in the morning)
- Alignment to ETMX by 3/7 morning
- 3/7: Y end pump down
- 3/7,8: leak test
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
2/27: ETMX release
- 2/23-3/10: Xend Pcal finalization 1
- Periscope installation
- Beam position by IR and Green
- 3/5 and 3/11~: ETMX seems to be hitting somewhere? Tuning was not enough(by Takahashi).
- 3/5: ETMX aligned with oplev accuracy
- 3/5-3/10: Xend Pcal finalization 2
- 3/5: AOS EY and EX(if they have time) work.
- 3/6: Green X alignment (no IR), and no hazard at Y end.
- 3/9-10(fastest, then 3/23): Pcal finalization
- 3/11, 18,19: Xend WAB finalization.
- 3/19: Heatlink etc.
- 3/19: ETMX finalization by Takahashi
- 3/21 closing
- 3/22 Pumping down
- Leak test
- 3/11~ : Night work starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- 2/18-3/22 DRMI commissioning
- 3/11-4/5 Y arm commissioning
- 3/25-4/5 FPMI commissioning
Discussion
- Plan of engineering runs with FPMI configuration in May.
- Drift monitor for Type A with low temperature.