 * Attendance: Miyakawa, Aso, Yokozawa, T.Yamamoto, Oshino
  * Zoom: Takahashi, Inoue, Hirose, Izumi
 * Attendance: Miyakawa, Cory, Pang, Oshino, Lucia, Tomura, Aso, Kozakai, Darhan
  * Zoom: Haino, Nakano, Ushiba, Washima, Inoue
Line 10: Line 10:
 * All alignment procedures are done on time.  * Payload diagonalization will take 3-4weeks at least.
 * DRMI experiment might not be done by the end of May.
 * ITMX warmup will determined on this week end.
Line 13: Line 15:
 * Mirror dirtiness. AR was dirty. We need estimate damage threshold.
  * Finger print was also found at viewport of SRM.
 * Yaw drift was seen due to touching cables inside.
 * Damping control for cryopayload is needed.
  * Specially for diagonalization of matrix of photo sensors for lock acquisition.
  * for long term, needs implementation of special filter for lock acquisition and sensitivity.
 * CAL group is thinking MC sensitivity monitor.
  * COM group needs even rough sensitivity monitor.

 * VIRGO group is interested in PEM monitors.
Line 28: Line 20:
 * Next meeting: 3/5.  * Next meeting: 3/26.

Minute of KAGRA commissioning meeting


  • Date: 2019/3/12 11:00AM~12PM
  • Attendance: Miyakawa, Cory, Pang, Oshino, Lucia, Tomura, Aso, Kozakai, Darhan
    • Zoom: Haino, Nakano, Ushiba, Washima, Inoue


Schedule

  • Payload diagonalization will take 3-4weeks at least.
  • DRMI experiment might not be done by the end of May.
  • ITMX warmup will determined on this week end.

Discussion


Others

  • Next meeting: 3/26.

KAGRA/Commissioning/Weekly/20190311/Minute (last edited 2019-03-12 12:25:20 by OsamuMiyakawa)