Differences between revisions 2 and 3
Revision 2 as of 2019-03-12 11:52:04
Size: 474
Comment:
Revision 3 as of 2019-03-12 12:25:06
Size: 481
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
  * Zoom: Haino, Nakano, Ushiba, Washima, Inoue,   * Zoom: Haino, Nakano, Ushiba, Washima, Inoue, Darhan

Minute of KAGRA commissioning meeting


  • Date: 2019/3/12 11:00AM~12PM
  • Attendance: Miyakawa, Cory, Pang, Oshino, Lucia, Tomura, Aso, Kozakai,
    • Zoom: Haino, Nakano, Ushiba, Washima, Inoue, Darhan


Schedule

  • Payload diagonalization will take 3-4weeks at least.
  • DRMI experiment might not be done by the end of May.
  • ITMX warmup will determined on this week end.

Discussion


Others

  • Next meeting: 3/26.

KAGRA/Commissioning/Weekly/20190311/Minute (last edited 2019-03-12 12:25:20 by OsamuMiyakawa)