Minute of KAGRA commissioning meeting


  • Date: 2019/3/12 11:00AM~12PM
  • Attendance: Miyakawa, Cory, Pang, Oshino, Lucia, Tomura, Aso, Kozakai, Darhan
    • Zoom: Haino, Nakano, Ushiba, Washima, Inoue


Schedule

  • Payload diagonalization will take 3-4weeks at least.
  • DRMI experiment might not be done by the end of May.
  • ITMX warmup will determined on this week end.

Discussion


Others

  • Next meeting: 3/26.