Minute of KAGRA commissioning meeting
- Date: 2019/3/26 11:00AM~12PM
- Attendance: Miyakawa, Nakano, Oshino, Yong-min, Aso, Yamamoto, Enomoto.
- Zoom: Takahashi, Sawada, Koseyama, Tomaru
Discussion
- It is better to have cavity when TF measurement is performed.
- ETMY cooling will start 4/10. We start some test during cooling, maybe 1 week or 2weeks after starting.
- Simple red/green status monitor is necessary.
Others
- Next meeting: 4/2 discussion for Type A strategy.