== 2019/5/7 Weekly commissioning meeting topics ==

 * Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
 * Assignment of staffs
  * [[https://teamup.com/kswnmta8p18h6u1uab]]


----
==== Schedule ====
 * Center
  * --(4/12: Pump down)--
  * --(4/29,30: Leak check)--
  * ~5/3: Vent and pumpdown
  * 5/9: leak check 

 * ITMX: 
  * --(4/2~: closing chamber and start pumping down.)--
  * --(4/10: Cooling starts.)--
  * 5/8: Cooling done

 * Xend
  * --(4/25: Pumpdown)--
  * --(5/2: leak check)--
  * --(5/2: Cooling start)--

 * Yend
  * --(4/4~: closing chamber and start pumping down.)--
  * --(4/10: Cooling starts.)--
  * 5/8: Cooling done

 * April: Measurement of TF, payload diagonalization on ITMX
 * End of April~: DRMI commissioning
 * End of April~: Y arm commissioning
 * ~End of May: FPMI commissioning
----
=== Discussion ===

 * Report for ITMY status for TF measurement and matrix diagonalization.
 * Y arm lock trial.
 * Beam hight issue on ITMs.

----