Minute of KAGRA commissioning meeting


  • Date: 2019/5/21 15:00~16:00
  • Attendance: Miyakawa, Tomura, Aso, Fabian, Federico, Ilene, Yamada, Washima, T.Tanaka, Kozakai, Yokozawa, Sugimoto, Michimura
  • Zoom: Miyoki, Inoue, Izumi, Kokeyama, Shoda, Nakano, Akutsu, Enomoto, Uchiyama, Takahashi


Summary of this week

  • Finesse measurement specially for Y arm several times, and results show Y arm is very lossy.

Discussion

  • No possibility gate valve is closed inside cavity(Aso).
  • X arm finesse today was ~1200 same as yesterday, bean spot is pretty centered.


Others

  • Next meeting: 5/28.