Line 10: Line 10:
 * --(5/22: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (BS) )--
Line 14: Line 13:
 * 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)
Line 23: Line 23:
  * 5/29: Cooling done
Line 48: Line 47:

Line 52: Line 49:
 *
 * DRMI

 * Engineering run

2019/5/28 11:00-12:00 Weekly commissioning meeting topics


Schedule

  • 5/22-23: MZ release from PSL

  • 5/20-24: Exchanging cryo valves.

  • 5/27-6/2: Y arm mass lock.
  • 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)

  • 6/3-6/14: Installation of TMS for ETMY
  • 6/8: Engineering run
  • ITMX
    • 5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm

    • 5/22AM~: tuned off shield cooler, finesse measurement for Xarm

  • ETMX
    • 5/2: Cooling start

  • ITMY
    • 5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm

  • ETMY
    • 5/17~: tuned off ETMY cryostat cooler

  • Long term:
    • 4/22-5/31: Yarm commissioning
    • 5/27-6/30: DRMI commissioning
    • 7/1-8/9: DRFPMI commissioning
    • 8/12-10/4: DRFPMI ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting


Discussion

Low finesse issue on Y arm

  • Finesse measurement:
    • Xarm 1451(1) with ITMX 73 K ETMX 120 K
    • Yarm 1312(5) with ITMY 65 K ETMY 75 K
  • Cryo status and plan
    • ETMs has no dew on 80K viewport but ITMs has still dew on their viewport.
  • DRMI
  • Engineering run


KAGRA/Commissioning/Weekly/20190528/Agenda (last edited 2019-05-28 10:52:09 by OsamuMiyakawa)