== 2019/5/28 11:00-12:00 Weekly commissioning meeting topics ==

 * Zoom URL: [[https://zoom.us/j/6676627462|https://zoom.us/j/6676627462]]
 * Assignment of staffs
  * [[https://teamup.com/kswnmta8p18h6u1uab]]


----
==== Schedule ====
 * --(5/22-23: MZ release from PSL)--
 * --(5/20-24: Exchanging cryo valves.)--
 * 5/27-6/2: Y arm mass lock.
 * 5/29: RT PC maintenance -> go to safe mode for all VIS connected Dolphin (specially BS)
 * 6/3-6/14: Installation of TMS for ETMY
 * 6/8: Engineering run

 * ITMX
  * --(5/22AM~: tuned off cryostat cooler, finesse measurement for Xarm)--
  * --(5/22AM~: tuned off shield cooler, finesse measurement for Xarm)--

 * ETMX
  * --(5/2: Cooling start)--

 * ITMY
  * --(5/23AM~: tuned off cryostat cooler, finesse measurement for Yarm)--

 * ETMY
  * --(5/17~: tuned off ETMY cryostat cooler)--

 * Long term:
  * 4/22-5/31: Yarm commissioning	
  * 5/27-6/30: DRMI commissioning
  * 7/1-8/9: DRFPMI commissioning
  * 8/12-10/4: DRFPMI ASC
  * 10/7-11/15: Post Commissioning
  * 11/18-12/13: Noise hunting


----
=== Discussion ===

==== Low finesse issue on Y arm ====
 * Finesse measurement:
  * Xarm 1451(1) with ITMX 73 K ETMX 120 K
  * Yarm 1312(5) with ITMY 65 K ETMY 75 K

 * Cryo status and plan
  * ETMs has no dew on 80K viewport but ITMs has still dew on their viewport.

 * DRMI

 * Engineering run

----