Differences between revisions 1 and 2
Revision 1 as of 2019-06-25 11:53:05
Size: 1454
Comment:
Revision 2 as of 2019-06-25 12:01:00
Size: 800
Comment:
Deletions are marked like this. Additions are marked like this.
Line 14: Line 14:
 * Results of finesse measurement looks a bit too high. Needs estimation of loss inside cavity for Yarm.
 * We should keep finesse measurement for going back the cooling down ITMY.

 * For DRMI preparations, optics, circuit, cabling, control models are almost ready.
  * Type A control test should be done during DRMI.
  * Type B and A needs some IFO as sensor.
 
 * Write manual if you experienced something.

 * CAL: MICH and DRMI calibration model is ready.

 * Remote work should be managed by calling to control room or sending email to gokagra.

 * Smooth transition for when watch dog is engaged has been implemented to Type B. It should be implemented to Type A.
  * When? -> Maybe tomorrow morning during maintenance time or the next week during DRMI.

 * Engineering run:
  * IMC is the first candidate which will be used for run. This is because Guardian is ready for only IMC, not for Michelson or X arm.
 * Needs check the gate valve were really open.
 * Location of spare mirror are not sure. At lease one GTAT mirror exists at Kashiwa campus, but we should have 6 spares.
 * Still we are not sore that we should have Erun on 7/13. It depends on schedule of opening chamber strongly.
Line 37: Line 21:
 * Next meeting: 5/28.  * Next meeting: 7/2.

Minute of KAGRA commissioning meeting


  • Date: 2019/6/25 11:00~12:00
  • Attendance: Miyakawa, Nakano, Ushiba, Miyo, Enomoto, Kozakai, Fabian, Ogaki, Matin, Yokozawa, Yamato, Darkhan, Oshino
  • Zoom: Mio, Eleonora, Sawada, Takahashi, Okutomi, Ohashi, Yamada, Izumi, Miyoki


Summary of last week

Discussion

  • Needs check the gate valve were really open.
  • Location of spare mirror are not sure. At lease one GTAT mirror exists at Kashiwa campus, but we should have 6 spares.
  • Still we are not sore that we should have Erun on 7/13. It depends on schedule of opening chamber strongly.


Others

  • Next meeting: 7/2.

KAGRA/Commissioning/Weekly/20190625/Minute (last edited 2019-06-25 12:01:00 by OsamuMiyakawa)