2019/7/16 11:00-12:00 Weekly commissioning meeting topics


Schedule

  • ~7/31: Trial for DRMI with polarization.
  • 7/6~: Trial for mass lock
  • ITMX
  • ETMX
  • ITMY
  • ETMY
  • Long term:
    • 4/22-5/31: Yarm commissioning

    • 5/27-6/30: DRMI commissioning

    • 7/1-8/9: FPMI/DRFPMI commissioning
    • 8/12-10/4: ASC
    • 10/7-11/15: Post Commissioning
    • 11/18-12/13: Noise hunting


Discussion

  • Issues
    • Polarization
    • Beam shape
    • Glitch on PRMI or DRMI
    • OMC
      • Low transmittance
      • 700Hz peak
      • Clipping
  • ER2
    • Trigger rate


Trigger rate during ER slides