Size: 1223
Comment:
|
← Revision 6 as of 2019-07-16 16:06:18 ⇥
Size: 720
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
* Attendance: Miyakawa, Aso, Nakano, Kozakai, Washima, Miyo, Yokozawa, Enomoto * Zoom: Sawada, Uchiyama, Inoue, Hiro Yamamoto, Ohashi, Uchiyama, Eleonora, Mio, Ushiba |
* Attendance: Miyakawa, Aso, Nakano, Kozakai, Washima, Miyo, Yokozawa, Enomoto, Yamada, Stefan, Ogaki * Zoom: Sawada, Uchiyama, Inoue, Uchiyama, Kokeyama, Shoda |
Line 9: | Line 9: |
=== Summary of last week === * ETMY misalignment was fixed. * Investigation of polarization is going on. * We keep central area for a while and keep DRMI characterization specially for control. * We confirmed that we would have an engineering run on 7/13. |
|
Line 17: | Line 11: |
* 12pm-6pm * PEM needs ~10min after run. * CAL needs free swinging Michelson. * Michelson * |
* Low finesse cavity can have mode hop in anywise, whether with/without polarization issue. * Needs changing Gouy phase by changing PR2(Stefan). * Leave beam shape mystery for a while without opening chamber. |
Line 23: | Line 15: |
* Action items for this month * Investigation for shape of reflection of both ITEX and ITMY. * P-pol shape with PRMI lock. * Rotating polarization of geen. * P-pol or S-pol monior * Control signal for PRMI/DRMI with polarization. * Education for DRMI from specialty. * Y arm lock with mass lock. * FPMI lock. * noise hunting. * PCAL line injection. * IOO noise hunting. * Dampin test mass. * OMC commissioning. * Simulation code for astigmatisms or something. |
* 1pm meeting will be more important. It discusses next 24hours commissioning tasks. * Commissioning leader should have the right to determine what is higher priority. |
Line 45: | Line 22: |
* Next meeting: 7/16. | * Next meeting: 7/23. |
Minute of KAGRA commissioning meeting
- Date: 2019/7/16 11:00~12:00
- Attendance: Miyakawa, Aso, Nakano, Kozakai, Washima, Miyo, Yokozawa, Enomoto, Yamada, Stefan, Ogaki
- Zoom: Sawada, Uchiyama, Inoue, Uchiyama, Kokeyama, Shoda
Discussion
- Low finesse cavity can have mode hop in anywise, whether with/without polarization issue.
- Needs changing Gouy phase by changing PR2(Stefan).
- Leave beam shape mystery for a while without opening chamber.
- 1pm meeting will be more important. It discusses next 24hours commissioning tasks.
- Commissioning leader should have the right to determine what is higher priority.
Others
- Next meeting: 7/23.