* --(4/22-5/31: Yarm commissioning)-- * --(5/27-6/30: DRMI commissioning)-- |
2019/7/16 11:00-12:00 Weekly commissioning meeting topics
Zoom URL: https://zoom.us/j/6676627462
- Assignment of staffs
Schedule
- ~7/31: Trial for DRMI with polarization.
- 7/6~: Trial for mass lock
- ITMX
- ETMX
- ITMY
- ETMY
- Long term:
- 7/1-8/9: FPMI/DRFPMI commissioning
- 8/12-10/4: ASC
- 10/7-11/15: Post Commissioning
- 11/18-12/13: Noise hunting
Discussion
- Status of FPMI
- DRFPMI plan
- Fiber noise cancellation