Line 11: Line 11:
2017/11/28 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171128.png||width=1200}}
2017/12/19 updated
{{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}}
Line 20: Line 20:
 * PR3-BS間ビーム位置測定(内山*、寺田、和泉)12/6-7予定。
Line 22: Line 21:
  * 12/11
  * 12/12
  * 12/13
  * 12/14
  * 12/15
  * 12/15 和泉、長野、川﨑、榎本
Line 28: Line 23:
 * GigEカメラセット
  * 12/15 苔山、川﨑
Line 29: Line 26:
 * BS PDセット
  * 12/15 横澤
Line 30: Line 29:
  
Line 59: Line 59:
 * Location: Control room, or educe  * Location: Control room, or eZuce
Line 62: Line 62:
2017/12/1(Fri.) 2017/12/20(Wed.)
Line 64: Line 64:
 * Daily
  * 作業
   * WS
    * 午後に片付けをする。
   * アラインメント
    * 昨日はあまり進展なし。PR3まで。今日うまくけばエンドで光が再び見えるはず。
    * 来週月火に真空作業があるため時間調整が必要。
 * 作業報告 (*:責任者)
  * Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
   * BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
   * スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
   * ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
    * Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
   * 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
Line 72: Line 72:
   * Type B:
    * Oplevに光が入った。もう少し解析に時間がかかる。大まかにはアラインメントはEYには向いている。
  * IMMTが動かない件
   * IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
   * DACカードの順序が入れ替わっているようである。->DGS
Line 75: Line 76:
   * Type A:
    * Y-endのケーブリングをしている。荷重テストと、YawのアラインメントをBFのピコモーターでする。ダンピングの進展具合は宮本君と確認。
  * IOO: 苔山、古畑、坂本、北澤
   * ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
   * MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
Line 78: Line 80:
 * 作業予定 (*:責任者)
  * Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
   * Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
Line 79: Line 84:
  * 作業人員(*:責任者)
   * WS: 麻生、*苔山、宮川 + 20名程度
   * アラインメント: 和泉、横澤、正田
   * Type B: Mark、 Enzo、平田、正田
   * Type A: 高橋、宮本
  * IOO
   * アラインメントがあるので、今日の作業は他のことをする。
Line 85: Line 87:
  * BS: Oplevの位置の初期化をしたい。
Line 86: Line 89:
  * Laser hazard
   * 今日からSRラインより奥に変更。
 * Laser hazard
   * センターはSR奥がハザードエリア。
   * 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
Line 90: Line 94:
  * 11/27の週
   * Commissioning Work Shop(11/27-12/1)
   * PRMの締め直しと、リリース。
   * メインビームの再アラインメント。
   * BSのダンピング
   * Type Aの接続
Line 97: Line 95:
  * 12/4の週
   * Type Aダンピングテスト。
   * メインビームの再アラインメント。
   * 月、火にIYCでの真空作業がある。
  * Week of 12/18
   * EYC閉止。
   * Type A引き続き調整。
   * ETMYのアラインメント。
Line 102: Line 100:
  * 12/11の週
   * ETMYからの戻り光確認。
   * 12/18EYC閉止。
 * Week of 12/25
  * 停電の可能性あり。
Line 108: Line 105:
   * 来週月、火に真空作業があり、ビームを止めて欲しいという要請が来ている。
Line 120: Line 117:
||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| ||
||11||2017/12/12||[[KAGRA/Commissioning/Weekly/20171212/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171212.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171212/Minute|Minute]]|| ||
Line 133: Line 132:
 * Meeting for pump down at ETMY ([[/Meetings/Others/20171213|Minute]], [[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171213.xlsx|schedule]])

KAGRA Commissioning Wiki


Task list


Schedule

2017/12/19 updated KAGRA/Commissioning/Commissioning_schedule_20171219.png


Working people assignment

* 責任者

  • ETMYアラインメント
    • 12/15 和泉、長野、川﨑、榎本
  • GigEカメラセット
    • 12/15 苔山、川﨑
  • BS PDセット
    • 12/15 横澤



Meetings


Morning meeting

  • Date and time: Every weekday, 9AM
  • Location: Control room, or eZuce

2017/12/20(Wed.)

  • 作業報告 (*:責任者)
    • Alignment of ETMY: *和泉、牛場、佐藤、都丸、高橋
      • BSからETMYはpitchに10uradくらいのズレがあったが、Oplevを見て戻すと特に問題なく光はエンドに当たった。
      • スリットを使う(三代木法)ことで、BS側に戻すのも相当順調だった。実際にスリットを外してすぐにBSのPDが反応した。
      • ETMYのPayloadのYawに200uradくらいの揺れが残っている。ヒートリンクに触ってしまった可能性が高い。ダンピングが必要。
        • Pitchも数十urad位揺れている。Pitchはおそらく上からのエアーで揺れている可能性が高い。
      • 光はYendで14000カウントでていたが、BSで6000カウントになった。予測とほぼ一致している。
    • IMMTが動かない件
      • IMMT2のYawのピコモーターが一方向には動くが、逆方向には動きにくい。手でネジを回すと一旦直る。すでに2-3度起きているので、再現性がありそう。
      • DACカードの順序が入れ替わっているようである。->DGS

    • IOO: 苔山、古畑、坂本、北澤
      • ISSのアラインメントがほぼ完了。AOMを触らなければならない時点でストップした。
      • MCのBURTがきちんと戻っていなかって、MCのサーボのゲインが間違っていたのでMCが不安定だった。直したら、安定になった。(和泉)
  • 作業予定 (*:責任者)
    • Alignment of ETMY: *和泉、高橋、牛場、都丸、宮本
      • Type Aの上の蓋を閉めて、全てリリースして、ダンピングをいれて1uradを目指す。
    • IOO
      • アラインメントがあるので、今日の作業は他のことをする。
    • BS: Oplevの位置の初期化をしたい。
  • Laser hazard
    • センターはSR奥がハザードエリア。
    • 昨日に引き続き、午後のある時点からYend 1Fがハザートエリアになる。
  • Weekly
    • Week of 12/18
      • EYC閉止。
      • Type A引き続き調整。
      • ETMYのアラインメント。
  • Week of 12/25
    • 停電の可能性あり。
  • 問題点など

KAGRA/Commissioning/DailyWork
<< <  2024 / 9 >  >>
Mon Tue Wed Thu Fri Sat Sun
            1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30            


Weekly meeting

  • Date and time: Every Tuesday, 11AM
  • Location: Meeting room at Hokubukaikan, or eZuce, Polycom

No.

Date

Agenda

Schedule

Minute

Files

12

2017/12/19

Agenda

Schedule

Minute

11

2017/12/12

Agenda

Schedule

Minute

10

2017/11/28

Agenda

Schedule

Minute

9

2017/11/14

Agenda

Schedule

Minute

8

2017/11/7

Agenda

Schedule

Minute

7

2017/10/31

Agenda

Minute

G1707278-v4

6

2017/10/24

Agenda

Minute

G1707278-v3

5

2017/10/17

Agenda

Minute

G1707278-v2
G1707298
G1707300

4

2017/10/10

Minute

G1707278-v1

3

2017/10/3

Agenda

Minute

Commissioning plan for phase1

2

2017/9/26

Agenda

Minute

Commissioning plan for phase1

1