Comment:
|
6962
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/14 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171213.png||width=1200}} |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 |
* *: responsible person * Re alignment * 1/11 *Izumi * 1/12 *Izumi |
Line 20: | Line 22: |
* ETMYアラインメント * 12/15 和泉、長野、川﨑、榎本 * GigEカメラセット * 12/15 苔山、川﨑 |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto |
Line 26: | Line 26: |
* BS PDセット * 12/15 横澤 |
* Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
Line 62: | Line 61: |
2017/12/15(Fri.) | 2017/1/11(Thrs.) |
Line 64: | Line 63: |
* Daily * 報告と作業 (*:責任者) |
* Remote participants by educe: None |
Line 67: | Line 65: |
* アラインメント: *和泉、長野、川崎、三代木 * BSのアルミ箔を外し、EYのPDに光をあてる。 * IMMT2のピコモーターがスタックしているようなのでそれを直す。 * EYのPDを回収して、スリットを使いEYのアラインメントをする。 * Type AのYawのダンピングがないので、50秒周期の揺れを待つ必要がある。Yawのアラインメントの待ち時間がキモ。 * BSで光が見えたらゴール。 |
* Report of work (*:responsible person) |
Line 74: | Line 67: |
* Type B(BS): *正田、和泉、長野 * TMだけでなく、IMにも返して、DC制御を含めたダンピングが改善された。UGFはPitch及びYawとも1Hz程度。40mHzのゲインで10万とか。COACHオンの状態で1uradまでになった。COACHオフだと十分アラインメントはできそう。 |
* Work plan (*:responsible person) * Alignment: *Izumi * Oplev, Re-alignment |
Line 77: | Line 71: |
* Type A(ETMY): *牛場、宮本 * 揺れはOplevでみて数uradになっている。 * アラインメントはなんとか出るところまでは持っていけた。 * PD設置: *横澤 * 和泉君の指示で移動のタイミングを横澤君に知らせる。 * BSカメラ設置: *苔山、長野 * 午後様子を見て問題がなければBS内が見えるようなカメラを設置する。外からの作業なので、他の作業と並行して作業可能。 * Laser hazard * センターは変わらずSR奥。 * 朝BSのY側のアルミ箔をとってYend 1Fをハザードエリアにする。今日の最後にBSのY側でアルミ箔で再び閉じる。 |
* Check of PLC at Yend for connection to measurement tools. * Laser hazard area * Behind of BS and SR line and Yend 1F |
Line 92: | Line 77: |
* Week of 1/8 * vacuum meeting 12:30 on 1/10, at fan hut. * Re-alignment for IFO on 1/11, 12. * Damping for ETMY on 1/13, 14. |
|
Line 93: | Line 82: |
* 12/11の週 * ETMYからの戻り光確認。 |
* Week of 1/15 * IOO works. * 1/19: Pump down. |
Line 96: | Line 86: |
* 12/18の週 * EYC閉止 |
* Week of 1/22 * 1/24,25 leak check. |
Line 99: | Line 89: |
* Issues | |
Line 100: | Line 91: |
* 問題点など |
|
Line 113: | Line 102: |
||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || ||12||2017/12/19||[[KAGRA/Commissioning/Weekly/20171219/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20171219.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20171219/Minute|Minute]]|| || |
|
Line 127: | Line 119: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/10 updated
Working people assignment
- *: responsible person
- Re alignment
- 1/11 *Izumi
- 1/12 *Izumi
- Damping for ETMY
- 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto
- Pump down
- 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人)
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/11(Thrs.)
- Remote participants by educe: None
- Report of work (*:responsible person)
- Work plan (*:responsible person)
- Alignment: *Izumi
- Oplev, Re-alignment
- Check of PLC at Yend for connection to measurement tools.
- Alignment: *Izumi
- Laser hazard area
- Behind of BS and SR line and Yend 1F
- Weekly
- Week of 1/8
- vacuum meeting 12:30 on 1/10, at fan hut.
- Re-alignment for IFO on 1/11, 12.
- Damping for ETMY on 1/13, 14.
- Week of 1/15
- IOO works.
- 1/19: Pump down.
- Week of 1/22
- 1/24,25 leak check.
- Week of 1/8
- Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)