Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/12/19 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20171219.png||width=1200}} |
2017/1/23 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
Line 17: | Line 17: |
* 責任者 * Green setting on PR2: * 12/26 *Akutsu, Yokogawa + 1 or 2 * 12/27 *Yokogawa + 1 or 2 |
* *: responsible person * Beam leading to REFP port * *Izumi |
Line 54: | Line 54: |
2017/12/22(Fri.) | 2017/1/29(Mon.) * Remote participants by eZuce: None |
Line 57: | Line 59: |
* Alignment of ETMY: *Ushiba, Takahashi, Tomaru, Miyamoto, Yokozawa * Fishing rodの高さ調整をした。オートレベラーを元にして、CALのカメラ、BFのLVDTを併用してキャリブレーションして合わせた。可動域の確認をした。 |
* Alignment * Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。 |
Line 61: | Line 64: |
* 停電のために真空層の蓋を閉める。(内山) | * Vacuum: leak check * Alignment: Oplevのセンタリング。 |
Line 64: | Line 68: |
* Laser hazard * センターはSR奥がハザードエリア。 |
* Laser hazard: Upstream of IMMT line |
Line 69: | Line 72: |
* Week of 12/18 * EYC閉止。 * Type A引き続き調整。 * ETMYのアラインメント。 |
* Week of 1/29 * 1/29,30 leak check. * 1/30 Opening ETMY gate valve. |
Line 74: | Line 76: |
* Week of 12/25 * Planed power outage in the afternoon on 12/25. |
* Week of 2/5 * 2/5 Cooling start. |
Line 79: | Line 81: |
* k1imcでDACの入れ替えが起こっている->以前WSの時に追加したらしい | * Network cableの整理 * ピコモーターの反応がなくなる。 |
Line 91: | Line 94: |
||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || ||14||2018/1/16||[[KAGRA/Commissioning/Weekly/20180116/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180116.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180116/Minute|Minute]]|| || ||13||2018/1/9||[[KAGRA/Commissioning/Weekly/20180109/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180109.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180109/Minute|Minute]]|| || |
|
Line 99: | Line 105: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 106: | Line 112: |
* Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/23 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/1/29(Mon.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment
- Yaw方向のジャンプは無くなった。Oplevの線形範囲程度(+/-数百mrad)でドリフトがあるもようだが、範囲は狭まって来ている。
- Alignment
- Work plan (*:responsible person)
- Vacuum: leak check
- Alignment: Oplevのセンタリング。
- Laser hazard: Upstream of IMMT line
- Weekly
- Week of 1/29
- 1/29,30 leak check.
- 1/30 Opening ETMY gate valve.
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- ピコモーターの反応がなくなる。
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)