Line 11: | Line 11: |
2017/1/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180116.png||width=1200}} |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/12(Fri.) | 2017/2/2(Fri.) |
Line 62: | Line 56: |
* Remote participants by educe: None * Affect of short power failure * VIS * EX のポラリティーが反転していた。瞬停と関係あるかは不明。 * IOO, AEL: *Kokeyama, Miyakawa, Kamiizumi * One of the power supply for 24V was broken after the short power failure. It was exchanged, then everything was recovered up to iMC. * DGS: It was found that autoburt did not work after 1/1. the new folder of 2018 was added and it is working now. |
* Remote participants by eZuce: Takahashi, Aso |
Line 74: | Line 59: |
* Alignment: *Izumi * X-armまでリカバーした。 * 中央エリア内の温度変化によりPR2とPR3のGASが上に上がってピッチが変わった。 * GASは真空槽を開けずに直せる範囲を超えている模様。 * PR3で100uradのオーダーでずれていた。 * Oplevの範囲内には入っているが、PRの曲率によりゼロ点意味をなさなくなっている。 |
* Vibration Isolation, * Restarted the BS realtime model. |
Line 81: | Line 62: |
* Alignment: Izumi * ETMY transfer function has a different shape when measured before. It means that ETMY might be touching somewhere. * For vertical, under BF was OK. * Yaw may be rotating too much. * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much. |
|
Line 82: | Line 68: |
* PLC at Yend: Aso * 発信機の信号を入れて見た。EPICSで取れるかどうか確認しようとしている。現在低温側が調整中。月曜に確認。 * Marionet Oplev: Akutsu * Oplevをおいて、光が返ってきていることを確認した。QPDまで入れたが、信号の確認はまだ。 |
|
Line 90: | Line 71: |
* Alignment: *Izumi * 真空曹を開けてPR2とPR3を直すかどうか。来週何日か時間をとって直したほうがよさそう。 |
|
Line 93: | Line 72: |
* Marionet Oplev: Akutsu * QPDの信号を確認する予定。 |
* Alignment: *Izumi, * We will rotate IP yaw to release somewhere suspected to touch. This work takes 1day at least. * Detchar for spectrum of suspension is necessary as soon as possible. |
Line 96: | Line 76: |
* Vacuum * Gate valve will be closed today. * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks. |
|
Line 97: | Line 80: |
* Laser hazard area * Behind of BS and SR line and Yend 1F |
* Type B * SR assembly continues. * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it. |
Line 101: | Line 86: |
* Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. * Week of 1/15 * IOO works. * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. |
|
Line 113: | Line 88: |
* 1/29 Cooling start | * 1/31-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 116: | Line 95: |
* EX のポラリティーが反転していた。回路の問題か? * 真空曹を開けてPR2とPR3を直すかどうか。 |
* EYA gate valve leaks. Urgency is minor. * ETMY BF may be touching? * The ETMY mirror showed a strange scattering pattern. |
Line 129: | Line 109: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || ||15||2018/1/23||[[KAGRA/Commissioning/Weekly/20180123/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180123.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180123/Minute|Minute]]|| || |
|
Line 139: | Line 121: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
Line 146: | Line 128: |
* Meeting for pump down and cooling at ETMY ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) | * Meeting for pump down and cooling at ETMY3 ([[/Meetings/Others/20180118|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY2 ([[/Meetings/Others/20180117|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) * Meeting for pump down and cooling at ETMY1 ([[/Meetings/Others/20180110|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20171204VacuumETMY|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/2(Fri.)
- Remote participants by eZuce: Takahashi, Aso
- Report of work (*:responsible person)
- Vibration Isolation,
- Restarted the BS realtime model.
- Alignment: Izumi
- ETMY transfer function has a different shape when measured before. It means that ETMY might be touching somewhere.
- For vertical, under BF was OK.
- Yaw may be rotating too much.
- After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much.
- ETMY transfer function has a different shape when measured before. It means that ETMY might be touching somewhere.
- Vibration Isolation,
- Work plan (*:responsible person)
- Alignment: *Izumi,
- We will rotate IP yaw to release somewhere suspected to touch. This work takes 1day at least.
- Detchar for spectrum of suspension is necessary as soon as possible.
- Vacuum
- Gate valve will be closed today.
- Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks.
- Type B
- SR assembly continues.
- Alignment: *Izumi,
- Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it.
- Weekly
- Week of 1/29
- 1/31-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- EYA gate valve leaks. Urgency is minor.
- ETMY BF may be touching?
- The ETMY mirror showed a strange scattering pattern.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)