8718
Comment:
|
9226
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/1/18 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180123.png||width=1200}} |
2017/1/30 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180130.png||width=1200}} |
Line 18: | Line 18: |
* Re alignment * 1/12 *Izumi |
|
Line 21: | Line 19: |
* Damping for ETMY * 1/13 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Miyakawa * 1/14 *Izumi, Ushiba, Okutomi, Shoda, Miyamoto, Arai, Miyo, Kozu, Yamamoto * Pump down * 1/19 *木村、都丸、(牛場)、高橋 or 奥富、和泉、阿久津、宮本 + 未経験者数名(技術系の人) |
* Beam leading to REFP port * *Izumi |
Line 60: | Line 54: |
2017/1/18(Thur.) | 2017/2/1(Thur.) |
Line 62: | Line 56: |
* Remote participants by educe: None | * Remote participants by eZuce: None |
Line 65: | Line 59: |
* Vacuum * Date of the pump down was postponed to 1/23(Tue.) due to the malfunction of yaw of ETMY. |
* Vacuum: *木村、上田、宍戸、高橋 * Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。 * EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず。 * 2mm下がって、0.5mm戻したような状態。しばらくは現状のまますすめて。来週もう一度トライする予定。 |
Line 68: | Line 64: |
* IOO: *Kokeyama * 1WがMCに入った。 |
* Alignment: 和泉、桐井、道村、奥富 * Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。 * LVDTのDACにオフセットを加えると現れる。 * エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。 * BSにも光は返ってきた。 * BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。 |
Line 71: | Line 71: |
* Alignment: *Izumi * ETMYのYawの挙動がおかしかったが、ピコモーターのチャンネル名のアサインの間違いだと判明。その後は問題なく動くようになった。 * Baffle PDの径ではBSからのビームが取れないことが判明。Baffle PDを動かして、PDが真ん中になるように動かしたのち、BSからのビームが確認できた。 * ETMYからの戻り光をリサージュで一晩降ったが見つかっていない。スリットを再び入れる予定。 |
* 機器制御のチェック: *麻生、日立造船 * センター、各エンド64chが使えるようになった。 |
Line 77: | Line 76: |
* Alignment: *Izumi * EYC, EYAの順にスリットを再び入れ、ETMYからの戻り光を確認する。 * 11時頃まで作業のためにレーザーハザードは全域。11時から通常のIMMより手前に戻す。 |
* Vacuum: *和泉、早河 * ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。 |
Line 81: | Line 79: |
* IOO: *苔山 * 今日一日光を使う。 |
|
Line 82: | Line 82: |
* 真空引きの最終判断は月曜日にする。 * チェックリスト最終確認。 * φ800フランジを閉める。 |
* Alignment: *和泉 * 午後にOplevの再センタリングをしたい。WABと時間調整。 |
Line 86: | Line 85: |
* Laser hazard: All area until 11AM, then changed to ipstream of IMM line. Hayakawa will change the border by 11AM. | * WAB: *阿久津 * 作業と重なるのでビームをできるだけ避けてほしい。アラインメントと時間調整。 * Type B * Blade inspection. * Re-centering oplev. * Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。 |
Line 90: | Line 95: |
* Week of 1/15 * 1/15~ baffle PD installation * 1/16~ IOO works. * 1/17: Vacuum check meeting * Week of 1/22 * 1/23: Pump down. * 1/29,30 leak check. |
|
Line 100: | Line 97: |
* 1/29 Cooling start | * 1/31-2/2 Re-checking main beam to ETMY * Week of 2/5 * 2/5 Cooling start. |
Line 105: | Line 105: |
* Cryostatがタッチしている可能性あり。 * ビームアラインメントの最終確認が時間的にぎりぎり。 |
* EYVのピストンのリリースで防振系がフリーにはならない。 * Leakが二箇所残っている。 |
Line 118: | Line 118: |
||16||2018/1/30||[[KAGRA/Commissioning/Weekly/20180130/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180130.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180130/Minute|Minute]]|| || | |
Line 129: | Line 130: |
||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| | ||4||2017/10/10|| || ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| |
KAGRA Commissioning Wiki
Task list
Schedule
2017/1/30 updated
Working people assignment
- *: responsible person
- Beam leading to REFP port
- *Izumi
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2017/2/1(Thur.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Vacuum: *木村、上田、宍戸、高橋
Gage valveが空いた。真空度はざっくりArm:1e-6 Cryo:1e-4で、徐々に平衡状態になっている。
- EYVの6本のピストンのうちの3本をリリースして防振系をフリーにしようとしたが、結局フリーにはならず。
- 2mm下がって、0.5mm戻したような状態。しばらくは現状のまますすめて。来週もう一度トライする予定。
- Alignment: 和泉、桐井、道村、奥富
- Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
- LVDTのDACにオフセットを加えると現れる。
- エンドでのビームはシャッターを開けたらすぐにETMYには届いたが、ゲートバルブが空いていなかったようで、バッフルPDに光が届かなかった。
- BSにも光は返ってきた。
- BSに光を返すとOplevで見てYawに線形領域を超えるくらいずれていた。
- Glitchの原因がどうやらLVDT関連の電気系である可能性が高まった。すくなくともメカ系ではなさそう。
- 機器制御のチェック: *麻生、日立造船
- センター、各エンド64chが使えるようになった。
- Vacuum: *木村、上田、宍戸、高橋
- Work plan (*:responsible person)
- Vacuum: *和泉、早河
- ゲートバルブにまずgate valveを開け、その後今日の午前にEYVの6本の足のうちの3本をリリースして防振系をフリーにする。
- IOO: *苔山
- 今日一日光を使う。
- Alignment: *和泉
- 午後にOplevの再センタリングをしたい。WABと時間調整。
- WAB: *阿久津
- 作業と重なるのでビームをできるだけ避けてほしい。アラインメントと時間調整。
- Type B
- Blade inspection.
- Re-centering oplev.
- Vacuum: *和泉、早河
- Laser hazard: 現在PSL。今日は午後のある時点でアラインメントのためSR2-3ラインより奥に変更。アラインメント完了後、PSLに戻す。
- Weekly
- Week of 1/29
- 1/31-2/2 Re-checking main beam to ETMY
- Week of 2/5
- 2/5 Cooling start.
- Week of 1/29
- Issues
- Network cableの整理
- EYVのピストンのリリースで防振系がフリーにはならない。
- Leakが二箇所残っている。
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)