9914
Comment:
|
10652
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/11(Wed.) === | |
Line 51: | Line 52: |
2017/3/19(Mon.) * Remote participants by eZuce: Kimura |
* Remote participants by eZuce: None |
Line 56: | Line 55: |
* IFO: Enomoto, Nagano, Nagano * RF signal was extracted from fringe of Michelson. * Ratio of ETMY and ETMX is not so large, roughly 1:1. * We need more damping for both ETMY and ETMX. * 4 front gate valve will be open. * Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD. |
|
Line 57: | Line 62: |
* VAC: *Uchiyama, Kimura, Suzuki * 4-5 turbo pumps started. * Currently vacuum level is ~1e-4Pa. * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again. * New control boxes for gate valve test were done. * Currently they work at local place, but they will be controlled remotely in the future. * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm. * PR2 assembly frames will be removed soon. * Power cable was connected to the ground at the power panel and made a short to the ground. |
* Camera: Yokozawa * Illuminator at X end chamber was installed. |
Line 67: | Line 65: |
* DAQ: Miyakawa, Yamamoto * k1tw0 started writing minute raw data. |
|
Line 71: | Line 69: |
* Camera: Inoue, Yokozawa * We check that nothing blocks the beam between EXA and EXC. |
|
Line 72: | Line 72: |
* Alignment, ETMY: *Izumi * All alignment after pump down will be checked. * PR3 yaw had some drift during pump-down. * Cal: * Calibration test using MC is planned on Wednesday. * VAC: Kimura, Sawada * Door will be closed at 3/23. * EX PD will be removed simonteninaously.: *Yokozawa |
* DAQ: *Miyakawa * Preparation to move writing minute raw of k1fw1 to a new k1tw1. |
Line 86: | Line 76: |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: PSL, Yend 1F * Green: off * [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off |
Line 92: | Line 90: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson * 4/13~ Pump down |
Line 97: | Line 96: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
* week of 4/16 * Michelson control * Leak check |
Line 101: | Line 100: |
* Issues | * week of 4/23 * Operation ==== Issues ==== |
Line 114: | Line 117: |
||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || ||23||2018/3/20||[[KAGRA/Commissioning/Weekly/20180320/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180320.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180320/Minute|Minute]]|| || |
|
Line 139: | Line 146: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/10 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/11(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: Enomoto, Nagano, Nagano
- RF signal was extracted from fringe of Michelson.
- Ratio of ETMY and ETMX is not so large, roughly 1:1.
- We need more damping for both ETMY and ETMX.
- 4 front gate valve will be open.
- Power of coil driver is too small at ETMX marionette damping. It will be exchanged to HPCD.
- Camera: Yokozawa
- Illuminator at X end chamber was installed.
- DAQ: Miyakawa, Yamamoto
- k1tw0 started writing minute raw data.
Work plan (*:responsible person)
- Camera: Inoue, Yokozawa
- We check that nothing blocks the beam between EXA and EXC.
- DAQ: *Miyakawa
- Preparation to move writing minute raw of k1fw1 to a new k1tw1.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: Upstream SR2-3 line, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
- Some controls for Michelson
- 4/13~ Pump down
- week of 4/16
- Michelson control
- Leak check
- week of 4/23
- Operation
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)